NIRCam News
December 20, 2005
Previous editions are available in the archive.
|
Tuesday Telecon
Tuesday, December 20, 1600 EDT
No telecon this week due to NIRCam monthly & NOTES TIM.
|
NIRCam Calendar
| Date |
Event |
Details |
| 12/20/05 |
NIRCam Monthly 0900 PDT
|
Palo Alto, CA |
| 12/20/05 |
NOTES TIM (following monthly) |
Palo Alto, CA |
| 12/21/05 |
FPA Housing CDR |
Palo Alto, CA |
| TBA |
GSE CDR |
Palo Alto, CA |
| 1/19/06 |
NIRCam Monthly |
Camarillo, CA |
| 1/24-26/06 |
JWST Mission SDR |
GSFC |
| late Jan/06 |
IRSU SRR |
GSFC |
| 1/31-2/2/06 |
JWST SWG |
Redondo Bch, CA |
| 2/2/06 |
NIRCam ICE CDR |
Palo Alto, CA |
| 2/8/06 |
NIRCam FPE CDR |
Palo Alto, CA |
| 2/9/06 |
FPA CDR |
Palo Alto, CA |
| TBD 5/06 |
ISIM Thermal PDR |
GSFC |
| 2/14/06 |
NIRCam FSW CDR |
Palo Alto, CA |
| 2/22-23/06 |
ISIM FSW PDR |
GSFC |
| 2/23/06 |
NIRCam Monthly |
Palo Alto, CA |
| 3/23/06 |
NIRCam Monthly |
Tucson, Az |
| 3/28/06 |
NIRCam I&T CDR |
Palo Alto, CA |
| 4/25-27/06 |
JWST Quarterly |
Noordwijk, Netherlands |
| 5/25/06 |
NIRCam Monthly |
GSFC |
| 6/22/06 |
NIRCam Monthly |
Palo Alto, CA |
| 7/20/06 |
NIRCam Monthly |
Palo Alto, CA |
| 8/31/06 |
NIRCam Monthly |
Palo Alto, CA |
|
Last Week's Accomplishments
NIRCam Activities for Week Ending 12/13/05
1) FPA CDR has had to be delayed because of problem with
the first delivery of flex cables. The problem is understood
and two paths including the baseline Dynaco cables have been
identified. CDR will be re-scheduled to early February.
2) Arizona hosted a successful visit by RSC QA personnel.
3) FPE box thermal analysis is complete.
4) Fact finding visit was paid to JDS Uniphase as part of the
bandpass filter vendor selection process.
5) Flight software has defined the dithering operation for
filter wheels and also completed another batch of unit testing.
|
|
NIRCam Top 5
| |
Item |
Status |
Action |
Next Report |
| 1 |
Requirements |
see below |
|
|
| 2 |
Bench cracks |
tests at Axsys 12/13-14 |
|
|
| 3 |
Detector Packaging |
|
|
|
| 4 |
NOTES/I&T |
Trade concluded - NOTES will be cold. |
|
|
| 5 |
Budget |
|
|
|
|
Document Status
| DRD |
Title |
Status |
Due |
Comments |
| SE-04 |
Verification Plan |
Rejected |
7/27/05 |
|
| IT-01 |
I&T Plan |
Rejected |
tbd |
On hold for resolution of NOTES testing plan. |
| SA-14 |
Safety Plan |
Review & Comment |
8/15/05 |
Delivered 7/29/05 |
|
Pending Changes
| Mod |
Mod Descr |
CCR # |
RTC# |
Description |
Cost/No |
Status |
Due |
Comments |
ECD |
| tbd |
Launch Slip |
|
|
22-mo Launch Slip, 10-mo delivery slip |
|
RFP |
11/28/05 |
proposal late |
|
| |
|
334 |
|
10-month delivery slip |
yes |
Complete |
|
|
|
| |
|
361 |
|
22-mo launch slip |
yes |
Complete |
|
|
|
| tbd |
Wave 5 |
|
|
Wave 5 Changes |
yes |
RFP |
|
waiting for IRD
|
|
| |
|
312 |
|
ISIM Reqts Doc Rev A |
yes |
Complete |
|
Adds reliability calcs |
|
| |
|
382 |
|
ISIM Reqts Doc Rev B |
|
CCB |
|
|
|
| |
|
TBD |
|
NIRCam Spec Rev D |
yes |
draft |
|
ISIM RD Rev B, IRD Rev D |
|
| |
|
313 |
|
SOW Rev E (Test Changes) |
Yes |
Complete |
|
|
|
| |
|
339 |
|
MAR Rev B |
Yes |
Complete |
|
Adds S/W QA |
|
| |
|
364 |
|
MICD EO# 1, 2, 3 |
Yes |
Complete |
|
|
|
| |
|
385 |
|
IRD Rev D |
Yes |
CCB |
|
|
|
| |
|
|
001D |
Synchronization |
Yes |
complete |
|
|
|
| |
|
|
008F |
Thermal |
|
complete |
|
|
|
| |
|
|
014C |
Stray Light |
|
complete |
|
|
|
| |
|
|
015G |
I&T Test Aids |
|
complete |
|
|
|
| |
|
|
017D |
On Orbit Sine |
|
complete |
|
|
|
| |
|
|
018A |
Radiative Heat Transfer |
|
complete |
|
|
|
| |
|
|
025B |
PIL Distortion |
|
complete |
|
|
|
| |
|
|
026D |
Mechanisms |
|
complete |
|
|
|
| |
|
|
028F |
ASIC |
|
complete |
|
|
|
| |
|
|
029B |
I&T Test Aids |
|
complete |
|
|
|
| |
|
|
031A |
PIL Source Location |
|
complete |
|
|
|
| |
|
|
032C |
WFS&C |
|
complete |
|
|
|
| |
|
|
033C |
Electrical TBRs |
|
complete |
|
|
|
| |
|
|
035A |
PIL WFE |
|
complete |
|
|
|
| |
|
|
037A |
FPA Isolation |
|
complete |
|
|
|
| |
|
|
038A |
ICE Harness Mass |
|
complete |
|
|
|
| |
|
|
042A |
Optical Cubes |
|
complete |
|
|
|
| |
|
|
043C |
Heater Voltage & Power |
|
complete |
|
|
|
| |
|
|
044B |
Cryo Metrology |
|
complete |
|
|
|
| |
|
|
045D |
WFS&C #2 |
|
complete |
|
|
|
| |
|
|
046D |
EMC #2 |
|
complete |
|
|
|
| |
|
|
047D |
WFS&C #3 |
|
complete |
|
|
|
| |
|
|
048C |
Optical Alignment |
|
complete |
|
|
|
| |
|
|
051C |
Thermal #2 |
|
complete |
|
|
|
| |
|
|
053A |
Electrical TBXs #2 |
|
complete |
|
|
|
| |
|
|
055A |
FSW Changes for ASIC |
|
complete |
|
|
|
| |
|
|
060A |
Typos & Misc Corrections |
|
complete |
|
|
|
| |
|
tbd |
|
NIRCam ETU Specification |
|
Loop 1 |
|
|
|
| tbd |
|
|
|
Wave 6 Changes |
|
|
|
|
|
| |
|
tbd |
|
IRD Rev E |
|
|
11/30/05 |
|
|
| |
|
|
030A |
FSW Telemetry Rate |
|
Loop 2 |
|
|
|
| |
|
|
034A |
Outgassing Rate |
|
Loop 1 |
|
|
|
| |
|
|
036A |
Structural Interface Load |
|
Loop 1 |
|
|
|
| |
|
|
041A |
Radiation |
|
Loop 2 |
|
|
|
| |
|
|
049A |
Handling Procedures |
|
Loop 1 |
|
|
|
| |
|
|
050A |
WFS&C #4 |
|
Loop 1 |
|
|
|
| |
|
|
052A |
Moving Target |
|
Loop 2 |
|
|
|
| |
|
|
054A |
Stray Light #2 |
|
Loop 1 |
|
|
|
|
NIRCam Needs
| Need |
Status |
ECD |
Assigned |
|
| Resolve TBXs in NIRCam Reqts Documents |
See "Pending Changes" above. |
7/31/05 TBR |
Lundquist |
|
| NIRCam Drill template to Axsys |
delayed by funding runout at GSFC |
10/15/05 |
Crow |
|
| Cryo refractive index measurements of Si |
Fused Silica complete |
|
Leviton |
|
| ASIC Ops Concept & interface documents |
TIM 12/2/2005 |
|
Dutta |
|
| Spacewire ICD & Spec |
|
|
Aguilar |
|
| Loads from harness/thermal straps |
|
|
Crow |
|
| Info on ground strap, if any |
|
|
McCloskey |
|
| SIDU Upgrade for ASIC |
|
|
Guy |
|
|
NIRCam TBD/TBR Progress & Plan

|
|
|
|