Logo

NIRCam News
December 12, 2005
Previous editions are available in the archive.

Tuesday Telecon

Tuesday, December 13, 1600 EDT

No telecon this week due to meeting at Axsys.

NIRCam Calendar
Date Event Details
12/13-14/05 OBA Status at Axsys Cullman, AL
12/20/05

NIRCam Monthly 0900 PDT

Palo Alto, CA
12/20/05 NOTES TIM (following monthly) Palo Alto, CA
To be rescheduled FPA & FPA Housing CDR Palo Alto, CA
TBA GSE CDR Palo Alto, CA
1/19/06 NIRCam Monthly Camarillo, CA
1/24-26/06 JWST Mission SDR GSFC
late Jan/06 IRSU SRR GSFC
1/31-2/2/06 JWST SWG Redondo Bch, CA
2/2/06 NIRCam ICE CDR Palo Alto, CA
2/3/06 NIRCam FPE CDR Palo Alto, CA
TBD 5/06 ISIM Thermal PDR GSFC
2/14/06 NIRCam FSW CDR Palo Alto, CA
2/22-23/06 ISIM FSW PDR GSFC
2/23/06 NIRCam Monthly Palo Alto, CA
3/23/06 NIRCam Monthly Tucson, Az
3/28/06 NIRCam I&T CDR Palo Alto, CA
4/25-27/06 JWST Quarterly Noordwijk, Netherlands
5/25/06 NIRCam Monthly GSFC
6/22/06 NIRCam Monthly Palo Alto, CA
7/20/06 NIRCam Monthly Palo Alto, CA
8/31/06 NIRCam Monthly Palo Alto, CA

Last Week's Accomplishments

NIRCam Activities for Week Ending 12/06/05

1) Held a very useful ASIC Operations TIM at Rockwell.
Many thanks to Markus Loose for his help.
2) Preparations for the FPA CDR are well underway with
SW FPA drawing set complete and the LW set in final review.
The FPA ICD is being released.
3) Fact finding visit was paid to Barr Associates in preparation
for final bandpass filter vendor selection.
4) ICE Box thermal analysis has been completed.
5) Production of the ZnSe ETU lenses has begun.
6) Optical test and alignment equipment such as a 4D
interferometer and the lens alignment station have started
arriving.

Announcements

Detector (FPA & Housing) CDR postponed to late January.

 

NIRCam Top 5
  Item Status Action Next Report
1 Requirements see below    
2 Bench cracks tests at Axsys 12/13-14    
3 Detector Packaging    

 

4 NOTES/I&T Trade concluded - NOTES will be cold.    
5 Budget      
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd On hold for resolution of NOTES testing plan.
SA-14 Safety Plan Review & Comment 8/15/05 Delivered 7/29/05
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd Launch Slip     22-mo Launch Slip, 10-mo delivery slip   RFP 11/28/05 proposal late  
    334   10-month delivery slip yes Complete      
    361   22-mo launch slip yes Complete      
tbd Wave 5     Wave 5 Changes yes RFP  

waiting for IRD

 
    312   ISIM Reqts Doc Rev A yes Complete   Adds reliability calcs  
    382   ISIM Reqts Doc Rev B   CCB      
    TBD   NIRCam Spec Rev D yes draft   ISIM RD Rev B, IRD Rev D  
    313   SOW Rev E (Test Changes) Yes Complete      
    339   MAR Rev B Yes Complete   Adds S/W QA  
    364   MICD EO# 1, 2, 3 Yes Complete      
    385   IRD Rev D Yes CCB      
      001D Synchronization Yes complete      
      008F Thermal   complete      
      014C Stray Light   complete      
      015G I&T Test Aids   complete      
      017D On Orbit Sine   complete      
      018A Radiative Heat Transfer   complete      
      025B PIL Distortion   complete      
      026D Mechanisms   complete      
      028F ASIC   complete      
      029B I&T Test Aids   complete      
      031A PIL Source Location   complete      
      032C WFS&C   complete      
      033C Electrical TBRs   complete      
      035A PIL WFE   complete      
      037A FPA Isolation   complete      
      038A ICE Harness Mass   complete      
      042A Optical Cubes   complete      
      043C Heater Voltage & Power   complete      
      044B Cryo Metrology   complete      
      045D WFS&C #2   complete      
      046D EMC #2   complete      
      047D WFS&C #3   complete      
      048C Optical Alignment   complete      
      051C Thermal #2   complete      
      053A Electrical TBXs #2   complete      
      055A FSW Changes for ASIC   complete      
      060A Typos & Misc Corrections   complete      
    tbd   NIRCam ETU Specification   Loop 1      
tbd       Wave 6 Changes          
    tbd   IRD Rev E     11/30/05    
      030A FSW Telemetry Rate   Loop 2      
      034A Outgassing Rate   Loop 1      
      036A Structural Interface Load   Loop 1      
      041A Radiation   Loop 2      
      049A Handling Procedures   Loop 1      
      050A WFS&C #4   Loop 1      
      052A Moving Target   Loop 2      
      054A Stray Light #2   Loop 1      
NIRCam Needs
Need Status ECD Assigned  
Resolve TBXs in NIRCam Reqts Documents See "Pending Changes" above. 7/31/05 TBR Lundquist  
NIRCam Drill template to Axsys delayed by funding runout at GSFC 10/15/05 Crow  
Cryo refractive index measurements of Si Fused Silica complete   Leviton  
ASIC Ops Concept & interface documents TIM 12/2/2005   Dutta  
Spacewire ICD & Spec     Aguilar  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  
SIDU Upgrade for ASIC     Guy  

NIRCam TBD/TBR Progress & Plan