Agenda:

NIRCam Calendar
Date Event Details
12/13-14/05 OBA Status at Axsys Cullman, AL
12/20/05

NIRCam Monthly @ ATC

Palo Alto, CA
12/21/05 FPA & FPA Housing CDR Palo Alto, CA
TBA I&T CDR Palo Alto, CA
TBA GSE CDR Palo Alto, CA
TBA FSW CDR Palo Alto, CA
1/19/06 NIRCam Monthly Camarillo, CA
1/24-26/06 JWST Mission SDR GSFC
late Jan/06 IRSU SRR GSFC
1/31-2/2/06 JWST SWG Redondo Bch, CA
late Jan 06 ICE & FPE CDRs Palo Alto, CA
TBD 2/06 ISIM Thermal PDR GSFC
2/22-23/06 ISIM FSW PDR GSFC
2/23/06 NIRCam Monthly Palo Alto, CA
3/23/06 NIRCam Monthly Tucson, Az
4/25-27/06 JWST Quarterly Noordvijk, Netherlands
5/25/06 NIRCam Monthly GSFC
6/22/06 NIRCam Monthly Palo Alto, CA
7/20/06 NIRCam Monthly Palo Alto, CA
8/31/06 NIRCam Monthly Palo Alto, CA

Last Week's Accomplishments

NIRCam Activities for Week Ending 11/22/2005

1) PI gave a talk on JWST to a conference on "IR Diagnostics of
Galaxy Evolution".
2) All the parts for an aluminum dummy FPA are in hand. The dummy will
be used to finalize assembly procedures.
3) Held a successful Straylight and Baffles CDR.
4) All ICE board layouts are complete.

Announcements

NIRCam ICE & FPE CDRs postponed (were 12/7-8/05) to late Jan/early Feb 2006.

Mitra Dutta is compiling another order of JWST-logo clothing. Click here for more information.

NIRCam Top 5
  Item Status Action Next Report
1 Requirements see below    
2 Bench cracks      
3 Detector Packaging    

 

4 NOTES/I&T   Warm NOTES?  
5 Budget      
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd On hold for resolution of NOTES testing plan.
SA-14 Safety Plan Review & Comment 8/15/05 Delivered 7/29/05
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd Launch Slip     22-mo Launch Slip, 10-mo delivery slip   RFP 11/28/05 proposal late  
    334   10-month delivery slip yes Complete      
    361   22-mo launch slip yes Complete      
tbd Wave 5     Wave 5 Changes yes RFP  

waiting for IRD

 
    312   ISIM Reqts Doc Rev A yes Complete   Adds reliability calcs  
    382   ISIM Reqts Doc Rev B   CCB      
    TBD   NIRCam Spec Rev D yes draft   ISIM RD Rev B, IRD Rev D  
    313   SOW Rev E (Test Changes) Yes Complete      
    339   MAR Rev B Yes Complete   Adds S/W QA  
    364   MICD EO# 1, 2, 3 Yes Complete      
    385   IRD Rev D Yes CCB      
      001D Synchronization Yes complete      
      008F Thermal   complete      
      014C Stray Light   complete      
      015G I&T Test Aids   complete      
      017D On Orbit Sine   complete      
      018A Radiative Heat Transfer   complete      
      025B PIL Distortion   complete      
      026D Mechanisms   complete      
      028F ASIC   complete      
      029B I&T Test Aids   complete      
      031A PIL Source Location   complete      
      032C WFS&C   complete      
      033C Electrical TBRs   complete      
      035A PIL WFE   complete      
      037A FPA Isolation   complete      
      038A ICE Harness Mass   complete      
      042A Optical Cubes   complete      
      043C Heater Voltage & Power   complete      
      044B Cryo Metrology   complete      
      045D WFS&C #2   complete      
      046D EMC #2   complete      
      047D WFS&C #3   complete      
      048C Optical Alignment   complete      
      051C Thermal #2   complete      
      053A Electrical TBXs #2   complete      
      055A FSW Changes for ASIC   complete      
      060A Typos & Misc Corrections   complete      
    tbd   NIRCam ETU Specification   Loop 1      
tbd       Wave 6 Changes          
    tbd   IRD Rev E     11/30/05    
      030A FSW Telemetry Rate   Loop 1 9/21/05 Aguilar  
      034A Outgassing Rate   Loop 1      
      036A Structural Interface Load   Loop 1      
      041A Radiation   Loop 1      
      049A Handling Procedures   Loop 1      
      050A WFS&C #4   Loop 1      
      052A Moving Target   Loop 2      
      054A Stray Light #2   Loop 1      
NIRCam Needs
Need Status ECD Assigned  
Resolve TBXs in NIRCam Reqts Documents See "Pending Changes" above. 7/31/05 TBR Lundquist  
MICD EO 4 & additional envelope for baffle Draft      
NIRCam Drill template to Axsys delayed by funding runout at GSFC 10/15/05 Crow  
Cryo refractive index measurements of Si, Fused Silica     Leviton  
ASIC Ops Concept & interface documents ops concept out for review   Dutta  
Spacewire ICD & Spec     Aguilar  
Loads update for OBA/ISIM brackets Delivered to Alison on 8/18   Crow  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  
SIDU Upgrade for ASIC     Guy  

NIRCam TBD/TBR Progress & Plan