Logo

NIRCam News
October 9, 2006
Previous editions are available in the archive.

Tuesday Telecon

Tuesday, October 10, 1600 EDT

Goddard Location: 22/C399A
Dial in info: 877-951-3250, Passcode 108321

Agenda: Mechanical: Workmanship vibe levels, loads from thermal strap & harness, RTC-81B (Static Envelope), RTC-67A (Alignment), RTC-71B (Struts)

NIRCam Calendar
Date Event Details
10/16-17/ 2006 Detector MRR U of Arizona
10/23-24/06 JWST SWG GSFC
10/23/06 IRSU PDR GSFC
10/24-26/06 ISIM PDR GSFC Area
10/31/06 NIRCam Monthly Video Only
11/28-30/06 JWST Quarterly Redondo Bch, CA
12/19/06 NIRCam Monthly Camarillo, CA
1/30-31/07 JWST T-NAR GSFC
Spring 2007 JWST Quarterly Dublin, Ireland

Last Week's Accomplishments

NIRCam Activities for Week Ending Oct 3, 2006

1) Submitted DRD SA-10, "Worst Caase Circuit Analysis" for
Goddard review.
2) Met with Dean Booher, GSFC QA Contractor on site in Tucson,
to discuss his participation in final cable assembly inspection and
in the cable MRR coming up.
3) AXSYS is moving NIRCam bench machining to the JWST building as that is the only way they think they can recover schedule on machining the replacement ETU bench.
4) Triplet testing which was delayed due to a spacer procurement problem is being expanded to include testing of the nudging process to provide a high fidelity test of the module-level alignment procedure.
5) New linear actuators for FAM testing have been received and are receiving a moly disulfide coating in preparation for life testing.
6) New sensor heads have been recieved and none show the epoxy
microcracking seen in earlier parts.

Announcements

NASA GSFC is closed Monday, Oct 9 for Columbus Day.

NIRCam Top 5
  Item Status Action Next Report
1 Detector Schedule Development units (3x) complete   MRR 10/16-17
2 Optical Bench Work restarted at Axsys    
3 Lens Triplet Cryo Test      
4 Filter Wheel Life Test with PFD    

 

5

Optical Alignment

Waiting for IT-01    
Document Status
DRD Title Status Due Comments
SA-02 Contamination Control Plan Returned for changes 9/8/2006 See JWST-MEMO-6835
SA-06 Materials Usage List Add'l Info Requested 10/18/2006  
SA-10 Worst Case Circuit Analysis In review 5/22/2006  
SA-14 Hazard Analysis Approved    
SE-04 Verification Plan Disapproved 11/8/2006 See JWST-MEMO-6957
SE-08 Inputs to IOS ICD Approved    
SE-09 Fault Protection Description Resubmitted    
SE-10 Math Models Returned with comments 11/8/2006 See JWST-MEMO-7015
IT-01 I&T Plan draft ETU I&T
-3 months
 
FSW-01 FSW Product Plan needs update   See JWST-MEMO-4063
FSW-02 FSW Vision Doc needs update   See-JWST-MEMO-4210
FSW-03 FSW Reqts Spec needs update   See JWST-MEMO-4167
OPS-11 Ops Concept needs update   See JWST-MEMO-4518
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd       Wave 6 Cost Changes yes RFP      
    543   NIRCam SOW Rev F yes Complete      
42       Wave 6 No-Cost   Complete      
    476   IRD Rev E no complete      
    584   IRD Rev F no complete      
    569   NIRCam Spec Rev E no complete      
        Attach N Applic. Doc. Matrix no complete      
    472   ISIM Reqts Doc Rev C no complete      
    562   ISIM Reqts Doc Rev D no complete      
    573   NIRCam ICD Rev B no complete      
    531   1553 Spec Rev A no complete      
    428   OTE Rx Rev B no complete      
tbd       Wave 7 Changes          
    593   ETU Spec   CCB - Reconcile comments  

D. Kelly/Julie

 
        IRD Rev G no   11/30/06    
      34E Outgassing Rate   Complete      
      54A Stray Light #2   hold 8/21/2006 S. Horner  
      56A Electrical Changes   Loop 1      
      65A FOV Changes     9/6/2006 B. Bos  
      66A Grounding   Loop 2   discuss 10/3  
      67A Alignment TBRs   Draft 9/6/2006 Crow/Davis  
      68A ICE Sync Changes   Loop 2      
      70B ICP A   Loop 2      
      71B K-mount Allocations   Loop 1   S. Horner  
      73A Telemetry Rate TBRs   Loop 2      
      74B MIPS   Loop 2      
      76A FSW Data Rate   Loop 2      
      78A Longwave Grism   Loop 1      
      79C FSW Changes   Loop 2      
      81B 1-G Envelope   Loop 2      
      82B Fuse Blow Transient   Loop 2      
      87A Post CDR Thermal Updates 2   Loop 2      
      88A WFS-DHS Positioning       A. Contos  
      89A EMC   Loop 2      
      90A Harness Update   Loop 1   Discuss 10/3  
      91A WFS Filters          
      92A MF Locations          
      93 A Voltage Ripple   Loop 1      
NIRCam Risks
Number Title Impact Likelihood Rating
NIRCam ISIM-Level Risks      
NIRCam-32 NIRCam Lens Mounts
C
A
Low
NIRCam-138 NIRCam Wavefront Error (low/mid/high sf)
D
B
Medium
NIRCam-143 NIRCam Optical Transmission
C
B
Low
NIRCam-191 NIRCam Detector BCS Failures
C
A
Low
NIRCam-250 NIRCam Region 1 Heat Transfer
B
C
Medium
NIRCam-251 NIRCam Optical Alignment
D
C
Medium
NIRCam-Level Risks      
28 OBA Damage
D
C
Medium
15 SCA Delivery Impacts I&T Schedule
D
C
Medium
4 Region 1 Heat Transfer
D
C
Medium
34 FPE to ASIC Harness Design
D
C
Medium
45 WFE due to Bench Distortion
C
D
Medium
80 Optical Throughput due to Contamination
C
D
Medium
33 I&T GSE Design and Fab not in time for I&T
C
C
Medium
35 Optical Triplets and DBS Mount Distortion
C
C
Medium
8 FPE Parts Qualification
C
C
Medium
78 WFE Degradation due to I&T tolerance exceedance
C
C
Medium
79 Optical throughput loss due to coatings
Medium
16 Sensitivity loss due to FPA/ASIC/FPE/cable noise
C
C
Medium
Review RFAs
Number Title Assigned To Due Date Status
NIRCAM Instrument Level CDR 5/23/2006      
JWST-NIRCam-CDR-001 Combined KM/NIRCam Systems Test A. Nordt 2/1/2007 Response Submitted
JWST-NIRCam-CDR-002 NIRCam Mechanical Disturbance Analysis & Verification A. Nordt 2/1/2007  
JWST-NIRCam-CDR-003 CPT 1 Test at 39K M. Pryor 2/1/2007  
JWST-NIRCam-CDR-004 Optics Mounts T. Kvamme 2/1/2007  
JWST-NIRCam-CDR-005 Systems I&T M .Pryor 2/28/2007  
JWST-NIRCam-CDR-006 Drawing status B. Steakley 7/15/2006 Response Submitted
JWST-NIRCam-CDR-007 Stray Light Baffle Coating B. Biggs 7/15/2006 Response Submitted
JWST-NIRCam-CDR-008 Focal plane assy cable soldering T. Magoncelli 7/15/2006 Closed
JWST-NIRCam-CDR-009 Filter wheel housing test temperatures S. McCully 9/15/2006 Late
JWST-NIRCam-CDR-010 EEE Parts T. King 9/15/2006 Closed
JWST-NIRCam-CDR-011 Optical Chain Workmanship Testing T. Kvamme 9/15/2006 Response submitted
JWST-NIRCam-CDR-012 ASIC Heatloads and Off-Baseline Case L. Osborne 9/15/2006 Closed
JWST-NIRCam-CDR-013 TV Test Cycles - Instrument Level M. Pryor 9/15/2006 Response submitted
JWST-NIRCam-CDR-014 TV Chamber Readiness M. Pryor 2/28/2007  
JWST-NIRCam-CDR-015 Optics Readiness Plan T. Kvamme 7/15/2006 Late
JWST-NIRCam-CDR-016 Beryllium Machining Plan A. Nordt 7/15/2006 Closed
JWST-NIRCam-CDR-017 ICE Harness Testing J. Thatcher 9/15/2006 Response submitted
JWST-NIRCam-CDR-018 ICE Power Card - decoupling capacitors J. Thatcher 9/15/2006 Closed
JWST-NIRCam-CDR-019 ICE CCA Design J. Thatcher 9/15/2006 Closed
JWST-NIRCam-CDR-020 PDPR/PR Plan Change M. Pryor 9/15/2006 Late
JWST-NIRCam-CDR-021 PIL Straylight L. Huff 9/15/2006 Response submitted
JWST-NIRCam-CDR-022 Measure S&P Reflectances L. Huff 9/15/2006 Late
JWST-NIRCam-CDR-023 Check etalon effects on optics L. Huff 9/15/2006 Late
JWST-NIRCam-CDR-024 Perform reliability analysis B. Bonner 9/15/2006 Late
NIRCam Subsystem CDRs      
Filter-1 Filter fishbone S. Horner    
Filter-3 Ghosting at Edges analysis Y. Mao    
Filter-9 Angle of incidence vs. OOB Y. Mao    
FPA-3 Shielding of temp sensor/heater cable T. Magoncelli    
FPA-4 Document shielding analysis B. Biggs    
FPA-5 Verify CMLBs not radioactive E. Young    
FPE-8 Reliability analysis of FPE/cable/ICP/ASIC/FPA T. Magoncelli    
FPE-9 Delivery schedule for cables T. Magoncelli   Response submitted - Shaune Allen to review
FPE-10 FPE cable length change impact T. Magoncelli    
FSW-1 Release FSW requirements document C. Cheng    
FSW-7 Resolve ASIC load format function (FPE vs. Ground); requirements for API call C. Cheng    
I&T-2 Risk of ETU non-verifications      
I&T-3 Volume measurement on ASMIF M. Pryor    
I&T-4 Correlate warm-to-cold models     Response submitted - Bill Eichhorn to review
I&T-5 Add test with SMART after FPA installed at Module M. Pryor    
I&T-6 Misalignments in forward and reverse directions     Response submitted - Bill Eichhorn to review
I&T-7 Provide alignment details M. Pryor    
I&T-8 Cold window transmission at 300K      
I&T-9 Vibrate OA with KMs M. Pryor   same as JWST-NIRCam-CDR-001
I&T-10 WFE of ambient optics, null lenses     John requests more study of ambient techniques

I&T-11

Define alignment budget items     John requests more analysis
I&T-12 Align GSE to optical references     Response submitted - John Hagopian to review
I&T-13 V1 up/down tests     Closed
I&T-14 Include figure uncertainty in alignment     John requests more analysis
I&T-15 VIRATAC on each optical element     John requests more analysis
I&T-16 Structural test of NIRCam bench M. Pryor    
ICE-5 Position sensor operation and cable length J. Thatcher    
ICE-7 Reliability of stack design and cables J. Thatcher    
ICE-9 Finalize connector design J. Thatcher    
ICE-10 Review position sensor cable spec. J. Thatcher   Response submitted - Shaune Allen to review
ICE-11 Verify sensor wire resistance meets requirement J. Thatcher    
ICE-12 Focus ICE description on ICE capability vs. flight software J. Thatcher    
ICE-17 Check command media vs. NASA parts stress J. Thatcher    
OBA-3 Peel test, shear test, stress analysis of bonded joints A. Nordt   Response submitted - John Johnston to review
OBA-4 Assess MS with FS=1.5 A. Nordt   Response submitted - John Johnston to review
OBA-8 SE to do independent tolerance analysis S. Horner    
Optic_mounts-29 Flat field source use.      
Baffles-3 Worst case clearance analysis B. Biggs    
Baffles-5 STOP analysis results, clearances B. Biggs    
Baffles-14 ASAP model to assess particles on POM      
NIRCam Needs Date Assigned Assigned to ECD Status
Need PSD information and details of mirror segments for higher fidelity coronagraphic modeling 8/31/2006 Pam Davila    
Harness and thermal strap loads on bench & struts 8/31/2006 John Crow    
Resolve ASIC jumpstart issue 8/31/2006 Mitra Dutta 10/31/06 Problem solved, ASIC IRCD needs update
Temp Sensors for Contam Prevention Heaters (ETU) 8/31/2006 Stu Glazer   Were due 6/8/06, needed by 11/3/06
ISIM CCDH FSW Rev 6.0 installed on SIDU including Spacewire interface and function call for ASIC micro-codes 8/31/2006 Mark Voyton   Not until Jan 2007
Release Rev B of ICD with Thermal Info 8/31/2006 Julie   complete
Resolution of Rogue Path 8/31/2006 Pam Davila   ??
Resolve open TBXs in IRD & ISIM Reqs Doc 8/31/2006 Julie    
Resolve open RTCs in IRD, ISIM Reqts, ICD 8/31/2006 Julie    
Define intermediate thermal stationing of harnesses 9/26/2006 Ray L    
Clarify workmanship vibe levels 9/26/2006 John Crow    
Acronym List
ASIC Application-Specific Integrated Circuit
ASMIF Ambient Science Instrument Mechanical Interface Fixture
BCS Balance Composite Structure
CCDH Common Command & Data Handling
CMLB Ceramic Multi-Layer Board
CPT Comprehensive Performance Test
DBS Dichroic Beam Splitter
DHS Dispersed Hartmann Sensor
EEE Electrical, Electronic, and Electromechanical (Parts)
ETU Engineering Test Unit
FOV Field of View
FPA Focal Plane Assembly
FPE Focal Plane Electronics
FSW Flight Software
GSFC Goddard Space Flight Center
GSE Ground Support Equipment
I&T Integration & Test
ICD Interface Control Document
ICE Instrument Control Electronics
ICP Interconnect Panel
IRD Interface Requirements Document
IOS ISIM-to-OTE-and-Spacecraft
ISIM Integrated Science Instrument Module
KM Kinematic Mount
MIPS Million Instructions Per Second
MRR Manufacturing Readiness Review
NGIN Next Generation Integrated Network
OA Optics Assembly
OBA Optical Bench Assy
OOB Out of Band
OTE Optical Telescope Element
PDR Preliminary Design Review
PFD Passive Friction Device
PIL Pupil Imaging Lens
PSD Power Spectral Density
RFA Request for Action
RTC Request for Technical Coordination
Rx Prescription
SCA Sensor Chip Assembly
SOW Statement of Work
STOP Structural, Thermal, Optical (Analysis)
SWG Science Working Group
TBR To Be Reviewed
TIMs Technical Interchange Meeting
T-NAR Technology Non-Advocate Review
TV Thermal Vacuum
UPS Uninterruptible Power Supply
WFE Wavefront Error
WFS Wavefront Sensing