NIRCam
News
October 1, 2007
Previous editions are available in the archive.
Tuesday Telecon
|
Date |
Meeting Agenda |
GSFC Location |
| Oct 2, 2007, 4pm EDT | Harness Routing Bench Status |
Bld 22 rm 399A |
|
Oct 9, 2007, 4 pm EDT |
Bench Status |
Bld 22 rm 399A |
Announcements
Other Telecons
| NIRCam Alignment Tiger Team meeting | No meeting this week | |
NIRCam Calendar
|
Date |
Event |
Details |
| Oct 18, 2007 |
NIRCam Monthly |
Palo Alto |
| Oct 23-24, 2007 | JWST SWG Meeting | STScI |
| Oct 25-26, 2007 | ICDH CDR | GSFC |
| Nov 6-8, 2007 |
JWST Partners Workshop |
Maryland |
| Nov 27-29, 2007 |
OTE PDR |
NGST? |
| Dec 4-5, 2007 | IOTA-ISIM Optical Test Audit | NGST ECO |
| Dec 12, 2007
|
NIRCam Monthly
|
Palo Alto
|
| Upcoming ISIM CDRs | ||
| Jan 29, 2008 | ISIM Region 2 and Harness Radiatior PDR | |
| Jan 31-Feb 1, 2008 | ISIM Structure CDR | |
| TBD Feb, 2008 | ISIM Flight Software CDR | |
| April 23, 2008 | IRSU CDR | |
| Mar 31- Apr 4, 2008 | JWST PDR | GSFC, Bld 8 Aud |
| 1st week of June, 2008 | ISIM Thermal Control CDR | |
| Sept 8-11, 2008 | ISIM CDR | GSFC |
1) NIRCam personnel visited Axsys to review the test report from mirror work.
2) NIRCam Science Team members participated in the JWST conference and held a
team meeting.
3) Substantial progress has been made in pulling in the FAM bearing schedule so the impact to
flight delivery is being greatly reduced.
|
DRD |
Title |
Status |
Due |
Comments |
|
SA-02 |
Contamination Control Plan |
Under Review |
See JWST-MEMO-6835, requested for resubmittal last June. |
|
|
SE-04 |
Verification Plan |
GSFC Review |
3/6/2007 |
|
|
SE-10 |
Math Models |
Returned with comments |
11/8/2006 |
See JWST-MEMO-7015 regarding mechanical models only, partially rejected in August with requested resubmittal in 90 days. |
|
PM-01 |
Project Management Plan |
Under Review |
|
|
|
FSW-01 |
FSW Product Plan |
needs update |
|
See JWST-MEMO-4063 |
|
FSW-02 |
FSW Vision Doc |
needs update |
|
See-JWST-MEMO-4210 |
|
FSW-03 |
FSW Reqts Spec |
returned w/ comments |
1/9/2007 |
Accepted with comments in mid-November with a requested update
due in 60 days (mid-January) |
|
OPS-11 |
Ops Concept |
needs update |
|
See JWST-MEMO-4518 |
Pending Changes (needs updating)
|
Mod |
CCR # |
RTC# |
Description |
Cost |
Status |
Due |
Comments |
|
|
|
|
|
|
|
|
|
ISIM Level NIRCam Risks (needs updating)
|
Number |
Title |
Impact |
Likelihood |
Rating |
|
NIRCam-32 |
NIRCam Lens Mounts |
C |
A |
Low |
|
NIRCam-138 |
NIRCam Wavefront Error (low/mid/high sf) |
D |
B |
Medium |
|
NIRCam-143 |
NIRCam Optical Transmission |
C |
B |
Low |
|
NIRCam-191 |
NIRCam Detector BCS Failures |
C |
A |
Low |
|
NIRCam-250 |
NIRCam Region 1 Heat Transfer |
B |
C |
Medium |
|
NIRCam-251 |
NIRCam Optical Alignment |
C |
B |
Low |
|
NIRCam -280 |
Extra Module-level cryotest with FPAs integrated |
|
|
|
|
Acronym List |
|
|
ASIC |
Application-Specific Integrated Circuit |
|
ASMIF |
Ambient Science Instrument Mechanical Interface Fixture |
|
BCS |
Balance Composite Structure |
|
CCDH |
Common Command & Data Handling |
|
CMLB |
Ceramic Multi-Layer Board |
|
CPT |
Comprehensive Performance Test |
|
DBS |
Dichroic Beam Splitter |
|
DHS |
Dispersed Hartmann Sensor |
|
EEE |
Electrical, Electronic, and Electromechanical (Parts) |
|
EOL |
End-of-life |
|
ETU |
Engineering Test Unit |
|
FOV |
Field of View |
|
FPA |
Focal Plane Assembly |
|
FPE |
Focal Plane Electronics |
|
FSW |
Flight Software |
|
GSFC |
|
|
GSE |
Ground Support Equipment |
|
I&T |
Integration & Test |
|
ICD |
Interface Control Document |
|
ICE |
Instrument Control Electronics |
|
ICP |
Interconnect Panel |
|
IRD |
Interface Requirements Document |
|
IOS |
ISIM-to-OTE-and-Spacecraft |
|
ISIM |
Integrated Science Instrument Module |
|
KM |
Kinematic Mount |
|
MIPS |
Million Instructions Per Second |
|
MRR |
Manufacturing Readiness Review |
|
NGIN |
Next Generation Integrated Network |
|
OA |
Optics Assembly |
|
OBA |
Optical Bench Assy |
|
OOB |
Out of Band |
|
OTE |
Optical Telescope Element |
|
PAR |
Pupil Alignment Reference |
|
PDR |
Preliminary Design Review |
|
PFD |
Passive Friction Device |
|
PIL |
Pupil Imaging Lens |
|
PSD |
Power Spectral Density |
|
RFA |
Request for Action |
|
RTC |
Request for Technical Coordination |
|
Rx |
Prescription |
|
SCA |
Sensor Chip Assembly |
|
SOW |
Statement of Work |
|
STOP |
Structural, Thermal, Optical (Analysis) |
|
SWG |
Science Working Group |
|
TBR |
To Be Reviewed |
|
TIMs |
Technical Interchange Meeting |
|
T-NAR |
Technology Non-Advocate Review |
|
TV |
Thermal Vacuum |
|
UPS |
Uninterruptible Power Supply |
|
WFE |
Wavefront Error |
|
WFS |
Wavefront Sensing |