Logo

NIRCam News
September 6 , 2005
Previous editions are available in the archive.

Tuesday Telecon

Tuesday, September 6, 1600 EDT
Goddard Location: 22/C399
Dial in information: 877-951-3250, Passcode 108321

Agenda: RTCs 045 & 047 (WFS&C), and 048 (optical alignment)

NIRCam Calendar
Date Event Details
9/6/05 WFS&C RTCs Mtg (045,047,048) 1600 EDT
9/8/05 Optics RTC Mtg (015, 044) 1300 EDT
9/8/05 Stray Light RTC Mtg (014,054) 1600 EDT
9/21/05 NIRCam Monthly GSFC
9/22-23/05 JWST SWG STScI
9/27/05 ICE CDR Palo Alto, CA
9/28/05 FPE CDR Palo Alto, CA
9/29/05 FSW CDR Palo Alto, CA
9/30/05 Detector BCS Failure Closure Review Camarillo, CA
10/5/05 ETU Stray Light/Baffle CDR Palo Alto, CA
10/6/05 FPA Housing CDR Palo Alto, CA
10/4/05 I&T CDR Palo Alto, CA
10/5-6/05 GSE CDR Palo Alto, CA
10/11-12/05 Optics Summit Greenbelt, MD ECO
10/25-26/05 ISIM EMC Summit GSFC
10/27/2005 ISIM Harness TIM GSFC

Last Week's Accomplishments

NIRCam Activities for Week Ending 8/30/05

1) Held a review of SCA acceptance testing procedures at Rockwell.
2) LM ATC, Az, and GSFC folks worked hard to organize the numerous RTCs and TBXs so these can be finished in a timely manner.
3) The ACE board for ASIC prototype testing is complete and initial tests are underway.
4) FSW has completed the design and coding of the NIRCAM ICE control module and is now checking it out against an ICE simulator.

Announcements

The charts from the NIRCam monthly (8/25/2005) are available on NGIN as JWST-RPT-005462.


NIRCam Top 5
  Item Status Action Next Report
1 FY06 Funding detailed replan for $24M/10 mo case in work CCR for 10 month slip in work  
2 Requirements See below - stray light is particular emphasis    
3 Detector Packaging      
4 Detector BCS Failure    

8/10/05

5 Filter Wheel Accuracy      
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd On hold for resolution of NOTES testing plan.
SA-14 Safety Plan Review & Comment 8/15/05 Delivered 7/29/05
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd 3-mo schedule slip     3-Month Schedule Slip Yes pre-neg      
tbd Wave 4     Wave 4 Changes yes RELEASED 10/3/05    
    239   NIRCam SOW Rev D yes Complete   ASIC  
    243/333   DRD Rev F/G yes Complete   EEE Parts  
    164/235   DMGSER Rev -/A

yes

Complete      
25 Wv 5 No Cost     Wave 5 No Cost Changes no Complete 8/31/2005    
    332   DILS Rev G no complete   adds EEE parts  
    320   IRD Rev C no complete      
tbd Wave 5     Wave 5 Changes yes        
    334   10 month Schedule Slip yes CCB 8/17/05    
    313   SOW Rev E (Test Changes) Yes Complete      
    339   MAR Rev B Yes Draft   Adds S/W QA  
    312   ISIM Requirements Doc Rev A no Complete      
    tbd   Mechanical ICD thru EO2 no draft 9/2/2005 J. Abell  
    tbd   Mechanical ICD EO3 yes Loop 1   L1 released 9/1  
    tbd   NIRCam Spec Rev C   Loop 1      
    tbd   IRD Rev D   Draft 9/30/05    
      001C Synchronization Yes complete      
      008D Thermal   complete      
      014 Stray Light   Loop 1 L1 9/2 Mtg on 9/8  
      015D I&T Test Aids   Loop 1   Mtg on 9/8  
      017A On Orbit Sine   complete      
      018A Radiative Heat Transfer   complete      
      025B PIL Distortion   complete      
      026D Mechanisms   complete      
      028B ASIC   complete      
      029B I&T Test Aids   complete      
      031A PIL Source Location   complete      
      032C WFS&C   complete      
      033A Electrical TBRs   Loop 1 L1 9/2    
      034A Outgassing Rate   Loop 1 L1 9/7    
      035A PIL WFE   complete      
      037A FPA Isolation   Loop 1 L1 9/2    
      038A ICE Harness Mass   Loop 1 L1 9/8    
      041A Radiation   Loop 1 9/16/05 L1 released 9/2  
      042A Optical Cubes   complete      
      043A Heater Voltage & Power   Loop 1 L1 9/7    
      044A Cryo Metrology   Loop 1 L1 released Mtg on 9/8  
      045A WFS&C #2   Loop 2 L2 released Mtg on 9/6  
      046C EMC #2   Loop 2 L2 released    
      047A WFS&C #3   Loop 2 L2 released Mtg on 9/6  
      048A Optical TBXs   Loop 1 L1 released mtg on 9/13  
      049A Handling Procedures   Loop 1 L1 9/2    
      051A Thermal #2   Loop 1 L1 9/7    
      053A Electrical TBXs #2   Loop 1 L1 9/7    
      054A Stray Light #2   Loop 1 L1 9/2 D. Kelly  
tbd tbd tbd   IRD Rev E     11/30/05    
      030A FSW Telemetry Rate   Loop 1      
      036A Structural Interface Load   Loop 1      
      050A WFS&C #4   Loop 1      
      052A Moving Target   Loop 2      
      055A FSW Changes for ASIC   draft      
NIRCam Needs
Need Status ECD Assigned  
Requirements Baseline by July 31 See "Pending Changes" above. 7/31/05 TBR Lundquist  
Mechanical ICD EO2 release EO1 & EO2 7/26/05 Crow  
ASIC Ops Concept & interface documents ops concept out for review   Dutta  
Additional SWTS for SIDU+ #2 Jamie Dunn says ok. Need date?   Campbell  
Loads update for OBA/ISIM brackets Delivered to Alison on 8/18   Crow  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  

NIRCam TBD/TBR Progress & Plan