Tuesday Telecon
|
Date |
Meeting Agenda |
GSFC Location |
| Sept 4, 2007, 4pm EDT | ISIM FSW simulators Harness mockup planning |
Bld 22 rm 399A |
|
Sept 11, 2007, 4pm EDT |
|
Announcements
Other Telecons
| NIRCam Bench trade | Sept 5, 2007,1 pm EDT | Discuss trade matrix |
| NIRCam Alignment Tiger Team meeting | Sept 6, 2007, 2 pm EDT | |
NIRCam Calendar
|
Date |
Event |
Details |
|
|
NIRCam Strut TIM |
|
|
Sept 18, 2007 |
NIRCam Monthly |
Palo Alto, will start at 4pm EDT (1pm PDT) |
|
Sept 24-27, 2007 |
JWST Science Mtg |
Tucson |
| Oct 18, 2007 |
NIRCam Monthly |
Palo Alto |
| Oct 23-24, 2007 | JWST SWG Meeting | STScI |
| Nov 6-8, 2007 |
JWST Partners Workshop |
Maryland |
| Nov 27-29, 2007 |
OTE PDR |
NGST? |
| Dec 4-5, 2007 | IOTA-ISIM Optical Test Audit | NGST ECO |
|
Dec 12, 2007
|
NIRCam Monthly
|
Palo Alto
|
1) Cracks in SCA moly plates machined at Arizona
were discovered by Teledyne. Other plates still
at Arizona were cryo cycled and inspected with no
cracks found so these will be sent to Teledyne.
2) The crosshair portion of the Pathfinder test is
complete after additional warm tests were performed to
check for mechanical "play" in the bench attachments.
A small revision in the cams will be made.
3) Larry Burriesci has retired, and Alison Nordt has
returned and will take his place as the Instrument IPT.
4) Analyses in support of OTE and WFS Team requests are
underway.
|
DRD |
Title |
Status |
Due |
Comments |
|
SA-02 |
Contamination Control Plan |
Under Review |
See JWST-MEMO-6835, requested for resubmittal last June. |
|
|
SE-04 |
Verification Plan |
GSFC Review |
3/6/2007 |
|
|
SE-10 |
Math Models |
Returned with comments |
11/8/2006 |
See JWST-MEMO-7015 regarding mechanical models only, partially rejected in August with requested resubmittal in 90 days. |
|
PM-01 |
Project Management Plan |
Under Review |
|
|
|
FSW-01 |
FSW Product Plan |
needs update |
|
See JWST-MEMO-4063 |
|
FSW-02 |
FSW Vision Doc |
needs update |
|
See-JWST-MEMO-4210 |
|
FSW-03 |
FSW Reqts Spec |
returned w/ comments |
1/9/2007 |
Accepted with comments in mid-November with a requested update
due in 60 days (mid-January) |
|
OPS-11 |
Ops Concept |
needs update |
|
See JWST-MEMO-4518 |
Pending Changes (needs updating)
|
Mod |
CCR # |
RTC# |
Description |
Cost |
Status |
Due |
Comments |
|
|
|
|
|
|
|
|
|
ISIM Level NIRCam Risks (needs updating)
|
Number |
Title |
Impact |
Likelihood |
Rating |
|
NIRCam-32 |
NIRCam Lens Mounts |
C |
A |
Low |
|
NIRCam-138 |
NIRCam Wavefront Error (low/mid/high sf) |
D |
B |
Medium |
|
NIRCam-143 |
NIRCam Optical Transmission |
C |
B |
Low |
|
NIRCam-191 |
NIRCam Detector BCS Failures |
C |
A |
Low |
|
NIRCam-250 |
NIRCam Region 1 Heat Transfer |
B |
C |
Medium |
|
NIRCam-251 |
NIRCam Optical Alignment |
C |
B |
Low |
|
NIRCam -280 |
Extra Module-level cryotest with FPAs integrated |
|
|
|
|
Acronym List |
|
|
ASIC |
Application-Specific Integrated Circuit |
|
ASMIF |
Ambient Science Instrument Mechanical Interface Fixture |
|
BCS |
Balance Composite Structure |
|
CCDH |
Common Command & Data Handling |
|
CMLB |
Ceramic Multi-Layer Board |
|
CPT |
Comprehensive Performance Test |
|
DBS |
Dichroic Beam Splitter |
|
DHS |
Dispersed Hartmann Sensor |
|
EEE |
Electrical, Electronic, and Electromechanical (Parts) |
|
EOL |
End-of-life |
|
ETU |
Engineering Test Unit |
|
FOV |
Field of View |
|
FPA |
Focal Plane Assembly |
|
FPE |
Focal Plane Electronics |
|
FSW |
Flight Software |
|
GSFC |
|
|
GSE |
Ground Support Equipment |
|
I&T |
Integration & Test |
|
ICD |
Interface Control Document |
|
ICE |
Instrument Control Electronics |
|
ICP |
Interconnect Panel |
|
IRD |
Interface Requirements Document |
|
IOS |
ISIM-to-OTE-and-Spacecraft |
|
ISIM |
Integrated Science Instrument Module |
|
KM |
Kinematic Mount |
|
MIPS |
Million Instructions Per Second |
|
MRR |
Manufacturing Readiness Review |
|
NGIN |
Next Generation Integrated Network |
|
OA |
Optics Assembly |
|
OBA |
Optical Bench Assy |
|
OOB |
Out of Band |
|
OTE |
Optical Telescope Element |
|
PAR |
Pupil Alignment Reference |
|
PDR |
Preliminary Design Review |
|
PFD |
Passive Friction Device |
|
PIL |
Pupil Imaging Lens |
|
PSD |
Power Spectral Density |
|
RFA |
Request for Action |
|
RTC |
Request for Technical Coordination |
|
Rx |
Prescription |
|
SCA |
Sensor Chip Assembly |
|
SOW |
Statement of Work |
|
STOP |
Structural, Thermal, Optical (Analysis) |
|
SWG |
Science Working Group |
|
TBR |
To Be Reviewed |
|
TIMs |
Technical Interchange Meeting |
|
T-NAR |
Technology Non-Advocate Review |
|
TV |
Thermal Vacuum |
|
UPS |
Uninterruptible Power Supply |
|
WFE |
Wavefront Error |
|
WFS |
Wavefront Sensing |