Tuesday Telecon

Tuesday, August 30, 1600 EDT
Goddard Location: 22/C399
Dial in information: 877-951-3250, Passcode 108321

Agenda: RTCs TBD

NIRCam Calendar
Date Event Details
10/11-12/05 Optics Summit Greenbelt, MD (ECO)
9/20/05 NIRCam Monthly GSFC
9/21-22/05 JWST SWG STScI
9/27/05 ICE CDR Palo Alto, CA
9/28/05 FPE CDR Palo Alto, CA
9/29/05 FSW CDR Palo Alto, CA
9/30/05 (TBR) Detector BCS Failure Closure Review Camarillo, CA
10/5/05 ETU Stray Light/Baffle CDR Palo Alto, CA
10/6/05 FPA Housing CDR Palo Alto, CA
10/4/05 I&T CDR Palo Alto, CA
10/5-6/05 GSE CDR Palo Alto, CA
10/25-26/05 ISIM EMC Summit GSFC
10/27/2005 ISIM Harness TIM GSFC

Last Week's Accomplishments

NIRCam Activities for Week Ending 8/24/2005

1) Received first DHAS at Arizona.
2) Cryocycling and testing of prototype POM complete. No
"quilting" observed at operational temps, and WFE is better
than required. ETU Pickoff Mirror delivered.
3) Be Bench machining is progressing well with required tolerances
being met easily.
4) Reviewed PIL optical design with WFS team via telecon.

Announcements

The charts from the NIRCam monthly (8/25/2005) are available on NGIN as JWST-RPT-005462.


NIRCam Top 5
  Item Status Action Next Report
1 FY06 Funding detailed replan for $24M/10 mo case in work CCR for 10 month slip in work  
2 Requirements See below - stray light is particular emphasis    
3 Detector Packaging      
4 Detector BCS Failure    

8/10/05

5 Filter Wheel Accuracy      
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd On hold for resolution of NOTES testing plan.
SA-14 Safety Plan Review & Comment 8/15/05 Delivered 7/29/05
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd 3-mo schedule slip     3-Month Schedule Slip Yes pre-neg      
tbd Wave 4     Wave 4 Changes yes RFP tbd    
    239   NIRCam SOW Rev D yes Complete   ASIC  
    243/333   DRD Rev F/G yes Complete      
    235   DMGSER Rev A

yes

Complete      
tbd Wv 5 No Cost     Wave 5 No Cost Changes no RFP      
    332   DILS Rev G no complete   adds EEE parts  
    320   IRD Rev C no complete      
tbd Wave 5     Wave 5 Changes yes        
    334   10 month Schedule Slip yes CCB 8/17/05    
    313   SOW Rev E (Test Changes) Yes Complete      
    tbd   MAR Rev B Yes Draft   Adds S/W QA  
    312   ISIM Requirements Doc Rev A no Complete      
    tbd   NIRCam Spec Rev C          
tbd Wave 6     Wave 6 Changes          
    tbd   IRD Rev D   Draft      
      008D Thermal   Loop 3   complete  
      015C I&T Test Aids   Loop 3   rejected  
      017A On Orbit Sine   Loop 3      
      018A Radiative Heat Transfer   Loop 3      
      025B PIL Distortion   Loop 3      
      026D Mechanisms   Loop 3   complete  
      028B ASIC   Loop 3 9/2/05 Final comments  
      030A FSW Telemetry Rate   Loop 3      
      031A PIL Image & WFE   Loop 3      
      032C WFS&C   Loop 3   complete  
      001C Synchronization   Loop 3 9/2/05 Final comments  
      tbd TBD/TBR reduction   draft      
tbd tbd tbd   IRD Rev E          
      029A I&T Aids   Loop 1      
      033A Electrical TBRS   Loop 1      
      034A Outgassing Rate   Loop 1      
      035A PIL WFE   Loop 1      
      036A Structural Interface Load   Loop 1      
      041A Radiation   Loop 1      
      045A WFSC #2   Loop 2   new  
      046A EMC #2   Loop 2   new  
NIRCam Needs
Need Status ECD Assigned  
Requirements Baseline by July 31 See "Pending Changes" above. 7/31/05 TBR Lundquist  
Mechanical ICD EO2 release EO1 & EO2 7/26/05 Crow  
ASIC Ops Concept & interface documents ops concept out for review   Dutta  
Additional SWTS for SIDU+ #2 Jamie Dunn says ok. Need date?   Campbell  
Loads update for OBA/ISIM brackets Delivered to Alison on 8/18   Crow  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  

NIRCam TBD/TBR Progress & Plan