NIRCam News
August 10, 2005
Previous editions are available in the archive.
|
Tuesday Telecon
No telecon this week due to vacations.
|
NIRCam Calendar
| Date |
Event |
Details |
| 8/25/05 |
NIRCam Monthly |
Palo Alto, CA |
| 8/30/05 |
Stray Light/Baffle CDR |
Palo Alto, CA |
| 8/31/05 |
FPA Housing CDR |
Palo Alto, CA |
| 10/3-4/05 |
Optics Summit |
Greenbelt, MD (ECO) |
| 9/20/05 |
NIRCam Monthly |
GSFC |
| 9/21-22/05 |
JWST SWG |
STScI |
| 9/27/05 |
ICE CDR |
Palo Alto, CA |
| 9/28/05 |
FPE CDR |
Palo Alto, CA |
| 9/29/05 |
FSW CDR |
Palo Alto, CA |
| 10/2005 |
JWST Quarterly |
Cancelled |
| 10/4/05 |
I&T CDR |
Palo Alto, CA |
| 10/5-6/05 |
GSE CDR |
Palo Alto, CA |
|
Last Week's Accomplishments
NIRCam Activities for Week Ending 8/2/05
1) Held PIL CDR.
2) Held FAM CDR.
3) Presented 14 papers on NIRCam at the SPIE meeting.
4) Received the GL Scientific ULB test dewar at Arizona.
The dewar passed it accepetance test cooldown reaching 35K
with no problems.
5) NIRCam "ACE" board has reached an adequate level of
functionality to test the ASIC with commanding and synch
capabilities in place.
6) NIRCam FSW has added a module for downloading microcode
to the ASIC.
7) Finished initial requirements definition for GSE software.
|
Announcements
Richard Vassar will be on vacation Aug 8-19. Bruce Steakley will be covering for him.
Julie Van Campen is on vacation this week.
Marcia Rieke will be at a conference
Charts from recent NIRCam meetings are available on NGIN:
| NIRCam Thermal CDR |
JWST-RVW- |
|
NIRCam Top 5
| |
Item |
Status |
Action |
Next Report |
| 1 |
FY06 Funding |
detailed replan for $24M/10 mo case in work |
CCR for 10 month slip in work |
|
| 2 |
Requirements |
See below - stray light is particular emphasis |
|
|
| 3 |
Detector Packaging |
|
|
|
| 4 |
Detector BCS Failure |
|
|
8/10/05
|
| 5 |
Filter Wheel Accuracy |
|
|
|
|
Document Status
| DRD |
Title |
Status |
Due |
Comments |
| SE-04 |
Verification Plan |
Rejected |
7/27/05 |
|
| IT-01 |
I&T Plan |
Rejected |
tbd |
On hold for resolution of NOTES testing plan. |
| SA-14 |
Safety Plan |
Review & Comment |
8/15/05 |
Delivered 7/29/05 |
|
Pending Changes
| Mod |
Mod Descr |
CCR # |
RTC# |
Description |
Cost/No |
Status |
Due |
Comments |
ECD |
| tbd |
3-mo schedule slip |
|
|
3-Month Schedule Slip |
Yes |
Pre-neg |
|
|
|
| tbd |
Wave 4 |
|
|
Wave 4 Changes |
yes |
RFP |
tbd |
|
|
| |
|
239 |
|
NIRCam SOW Rev D |
yes |
Complete |
|
ASIC |
|
| |
|
243 |
|
DRD Rev F |
yes |
Complete |
|
|
|
| |
|
235 |
|
DMGSER Rev A |
yes
|
Complete |
|
|
|
| |
|
236 |
|
GFP List Rev. A |
yes |
Complete |
|
|
|
| |
|
268 |
|
Contract Attachment N |
no |
Complete |
|
|
|
| tbd |
Wave 5 |
|
|
Wave 5 Changes |
yes |
|
|
|
|
| |
|
334 |
|
10 month Schedule Slip |
yes |
CCB |
8/17/05 |
|
|
| |
|
313 |
|
SOW Rev E (Test Changes) |
Yes |
Complete |
|
|
|
| |
|
333 |
|
DRD Rev G |
no |
CCB |
8/17/05 |
Add EEE Parts |
|
| |
|
332 |
|
DILS Rev G |
no |
CCB |
8/17/05 |
Add EEE Parts |
|
| |
|
tbd |
|
MAR Rev B |
Yes |
Draft |
|
Adds S/W QA |
|
| |
|
320 |
|
IRD Rev C |
Yes |
CCB |
|
|
|
| |
|
|
019D |
NIRCam Discretes |
no |
Complete |
|
|
|
| |
|
|
020A |
Focus |
no |
Complete |
|
|
|
| |
|
|
021A |
Pupil Shear |
no |
Complete |
|
|
|
| |
|
|
022A |
Code Format |
no |
Complete |
|
|
|
| |
|
|
023C |
Launch Pressure Profile |
no |
Complete |
|
|
|
| |
|
|
024B |
V1 Down Testing |
no |
Complete |
|
|
|
| |
|
|
027B |
NIRCam Fault Protection |
no |
Complete |
|
|
|
| |
|
312 |
|
ISIM Requirements Doc Rev A |
|
CCB |
7/5/05 |
|
|
| |
|
tbd |
|
NIRCam Spec Rev C |
|
|
|
|
|
| tbd |
Wave 6 |
|
|
Wave 6 Changes |
|
|
|
|
|
| |
|
tbd |
|
IRD Rev D |
|
Draft |
|
|
|
| |
|
|
008D |
Thermal |
|
Loop 3 |
8/17/05 |
new Rev out |
|
| |
|
|
015C |
I&T Test Aids |
|
Loop 3 |
8/17/05 |
new Rev out |
|
| |
|
|
017A |
On Orbit Sine |
|
Loop 3 |
|
|
|
| |
|
|
018A |
Radiative Heat Transfer |
|
Loop 3 |
|
|
|
| |
|
|
025B |
PIL Distortion |
|
Loop 3 |
|
|
|
| |
|
|
026D |
Mechanisms |
|
Loop 3 |
8/17/05 |
new Rev |
|
| |
|
|
028B |
ASIC |
|
Loop 3 |
8/17/05 |
new Rev |
|
| |
|
|
030A |
FSW Telemetry Rate |
|
Loop 3 |
|
|
|
| |
|
|
031A |
PIL Image & WFE |
|
Loop 3 |
|
|
|
| |
|
|
032C |
WFS&C |
|
Loop 3 |
8/17/05 |
new Rev |
|
| |
|
|
001C |
Synchronization |
|
Loop 3 |
8/17/05 |
new Rev - its Back! |
|
| |
|
|
tbd |
TBD/TBR reduction |
|
draft |
|
|
|
| tbd |
tbd |
tbd |
|
IRD Rev E |
|
|
|
|
|
| |
|
|
029A |
I&T Aids |
|
Loop 1 |
|
|
|
| |
|
|
033A |
Electrical TBRS |
|
Loop 1 |
|
|
|
| |
|
|
034A |
Outgassing Rate |
|
Loop 1 |
|
|
|
| |
|
|
035A |
PIL WFE |
|
Loop 1 |
|
|
|
| |
|
|
036A |
Structural Interface Load |
|
Loop 1 |
|
|
|
| |
|
|
041A |
Radiation |
|
Loop 1 |
|
|
|
| |
|
|
045A |
WFSC #2 |
|
Loop 2 |
|
new |
|
| |
|
|
046A |
EMC #2 |
|
Loop 2 |
|
new |
|
|
NIRCam Needs
| Need |
Status |
ECD |
Assigned |
|
| Requirements Baseline by July 31 |
See "Pending Changes" above. |
7/31/05 TBR |
Lundquist |
|
| Mechanical ICD EO2 release |
EO1 & EO2 expected final by Bench CDR |
7/26/05 |
Crow |
|
| ASIC Ops Concept & interface documents |
ops concept out for review |
|
Dutta |
|
| Additional SWTS for SIDU+ #2 |
Jamie Dunn says ok. Need date? |
|
Campbell |
|
| Loads update for OBA/ISIM brackets |
|
|
Crow |
|
| Loads from harness/thermal straps |
|
|
Crow |
|
| Info on ground strap, if any |
|
|
McCloskey |
|
|
NIRCam TBD/TBR Progress & Plan

|
|
|
|