NIRCam Calendar
Date Event Details
7/25-26/05 WFSC Mini-PIT Boulder, CO
7/26-27/05 ICDH PDR GSFC
7/26/05 FIlter Wheel CDR Palo Alto, CA
7/27/05 PIL CDR Palo Alto, CA
7/28/05 3-DOF FAM CDR Palo Alto, CA
8/4/05 Thermal CDR Palo Alto, CA
8/8-9/05 NIRCam Science Team Mtg Palo Alto, CA
8/25/05 NIRCam Monthly Palo Alto, CA
8/31/05 FPA Housing CDR Palo Alto, CA
9/20/05 NIRCam Monthly GSFC
9/21-22/05 JWST SWG STScI
9/27/05 ICE CDR Palo Alto, CA
9/28/05 FPE CDR Palo Alto, CA
9/29/05 FSW CDR Palo Alto, CA
10/2005 JWST Quarterly Baltimore, MD

Last Week's Accomplishments

NIRCam Activities for Week Ending 7/19/05


1) Held a Stray Light TIM and identified missing requirements and areas where extra baffling would help if the instrument envelope could be expanded slightly.
2) Held a review of cryogenic refractive indices and settled on values for the ETU prescription which it is hoped will be the final prescription.
3) Produced simulations of deep surveys to check how far sensitivity can be relaxed and still identify first light objects.
4) Concluded contract negotiations for the "PAR2MAR" change.
5) Completed tech eval of 3-Month Slip proposal.

 

Announcements

Charts from recent NIRCam meetings are available on NGIN:

NIRCam Monthly 7/20/2005      JWST-RPT-005317
NIRCam Stray Light/Baffle TIM JWST-PRES-005308 & JWST-PRES-005309
NIRCam OBA CDR                    JWST-RVW-005322
Phil Sabelhaus' Project Status Charts JWST-PRES-005294

NIRCam Top 5
  Item Status Action Next Report
1 FY06 Funding detailed replan for $24M/10 mo case in work CCR for 10 month slip in work  
2 Requirements See below - stray light is particular emphasis    
3 Detector Packaging      
4 Detector BCS Failure    

7/13/05

5 Filter Wheel Accuracy   Expect resolution @ FWA CDR 7/26/05
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd On hold for resolution of NOTES testing plan.
SA-14 Safety Plan Rejected 6/23/2005 Need to work with J. Rauscher to resolve.
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd 3-mo schedule slip     3-Month Schedule Slip Yes Pricing      
tbd Wave 4     Wave 4 Changes yes RFP tbd dbl check in-house  
    207   NIRCam Spec Rev B (PDR) yes Complete      
    231   IRD Rev A. yes Complete      
    235   DMGSER Rev A

yes

Complete      
    236   GFP List Rev. A yes Complete      
    259   Mech GSE in Contract B.1 yes Complete      
    268   Contract Attachment N no Complete      
tbd Wave 5     Wave 5 Changes yes        
    334   10 month Schedule Slip yes CCR Comment      
    313   SOW Rev E (Test Changes) Yes CCB      
    333   DRD Rev G no CCR Comment   Add EEE Parts  
    332   DILS Rev G no CCR Comment   Add EEE Parts  
    tbd   MAR Rev B Yes Draft   Adds S/W QA  
    320   IRD Rev C Yes CCB? 7/8/05    
      019D NIRCam Discretes no Complete      
      020A Focus no Complete      
      021A Pupil Shear no Complete      
      022A Code Format no Complete      
      023C Launch Pressure Profile no Complete      
      024B V1 Down Testing no Complete      
      027B NIRCam Fault Protection no Complete      
    312   ISIM Requirements Doc Rev A   CCB 7/5/05    
    tbd   NIRCam Spec Rev C          
tbd Wave 6     Wave 6 Changes          
    tbd   IRD Rev D   Draft      
      008C Thermal   Loop 3      
      015B I&T Test Aids   Loop 3      
      017A On Orbit Sine   Loop 3      
      018A Radiative Heat Transfer   Loop 3      
      025B PIL Distortion   Loop 3      
      026C Mechanisms   Loop 3      
      028A ASIC   Loop 3      
      030A FSW Telemetry Rate   Loop 3      
      031A PIL Image & WFE   Loop 3      
      032B WFS&C   Loop 3      
      tbd TBD/TBR reduction   draft      
tbd tbd tbd   IRD Rev E          
      029A I&T Aids   Loop 1      
      033A Electrical TBRS   Loop 1      
      034A Outgassing Rate   Loop 1      
      035A PIL WFE   Loop 1      
      036A Structural Interface Load   Loop 1      
      041A Radiation   Loop 1      
NIRCam Needs
Need Status ECD Assigned  
Requirements Baseline by July 31 See "Pending Changes" above. 7/31/05 TBR Lundquist  
Mechanical ICD EO2 release EO1 & EO2 expected final by Bench CDR 7/26/05 Crow  
ASIC Ops Concept & interface documents ops concept out for review   Dutta  
Additional SWTS for SIDU+ #2 Jamie Dunn says ok. Need date?   Campbell  
Loads update for OBA/ISIM brackets     Crow  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  

NIRCam TBD/TBR Progress & Plan