NIRCam News
July 17, 2006
Previous editions are available in the archive.

Tuesday Telecon

Tuesday, July 18, 1330 EDT (Note earlier start time!)

Goddard Location: 22/C399A

Dial-in: 877-951-3250, Passcode 108321

Agenda: Discuss comments to Verification Plan

NIRCam Calendar
Date Event Details
7/20/06 NIRCam Monthly Camarillo, CA
7/25-26/06 ISIM Verification and I&T Summit GSFC Area
7/27/06 K-Mount TIM GSFC
8/16-18/06 ISIM PDR Dry Run #1 GSFC
8/24-25/06 NIRCam Sciecne Team Mtg Tucson, AZ
8/31/06 NIRCam Monthly Palo Alto, CA
9/6-8/06 ISIM PDR Dry Run #2 GSFC
9/12-14/06 Eclipse SRR Redondo Bch, CA
9/21/06 NIRCam Monthly Palo Alto, CA
10/2-4/06 ISIM PDR Final Dry Run GSFC
10/23-24/06 JWST SWG GSFC
10/23/06 IRSU PDR GSFC
10/24-26/06 ISIM PDR GSFC Area
10/27/06 NIRCam Monthly GSFC
11/21/06 NIRCam Monthly Camarillo, CA
11/28-30/06 JWST Quarterly Redondo Bch, CA
12/19/06 NIRCam Monthly Palo Alto, CA

Last Week's Accomplishments

NIRCam Activities for Week Ending July 11, 2006

1) NIRCam Internal Be Fracture Investigation Team started
work, and began filling in a fishbone analysis.
2) Arizona FPA Team held a document and procedure review
with Rockwell for cable assemblies.
3) Received word from Goddard that the Hytek boards used
in the cable assembly passed DPA and amy be used for flight
cabels assemblies.
4) All parts have been received and are in cleaning for
the Filter Wheel Assembly prototype re-build including a
passive friction device.
5) MOOG has shown the damaged harmonic drive from the FAM
linear actuator test to the manufactor who stated that the dmage
was mostly likely from inadequate lubricant as had been thought
by the NIRCam Team.
6) The first cold test of the beamsplitter has been run and the
part meets specs. This test was run without a mount to isolate
effects due to the coatings, and just tested the front side. The
back side will be tested shortly and a full up mounted test will
occur later.


Announcements

 

NIRCam Top 5
  Item Status Action Next Report
1 Optical Bench Damage Mtg at Axsys 7/12-13    
2 Detector Packaging & Test     at Monthly 7/20
3 Lens Triplet Cryo Test      
4 Filter Wheel Life Test with PFD    

 

5

Electronics drawing release

     
Document Status
DRD Title Status Due Comments
IT-03 Instrument and GSE Ground Transportation Plan Returned for minor corrections 6/5/2006  
PM-01 Project Management Plan Approved    
SA-02 Contamination Control Plan Returned for changes 6/5/2006  
SA-06 Materials Usage List Returned - incomplete 6/9/2006  
SA-07 As Designed Parts List Approved    
SA-08 Parts Database Approved    
SA-09 Parts Stress Analysis Approved    
SA-14 Hazard Analysis Returned - Minor Comments 6/5/2006  
SE-04 Verification Plan Distr for Review 6/9/2006 Need mtg or telecon to work issues - 7/18/06
SE-08 Inputs to IOS ICD Approved    
SE-09 Fault Protection Description Returned with comments    
SE-10 Math Models Returned with comments    
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd       Wave 6 Cost Changes yes        
    476   IRD Rev E yes complete      
        NIRCam ETU Spec no        
        NIRCam SOW Rev F yes out for comment   NOTES testing, Grism  
tbd       Wave 7 Changes          
        IRD Rev F no        
      34 Outgassing Rate          
      54 Stray Light #2          
      56 IRSU          
      65 FOV Changes          
      68 ICE Sync Changes          
      70 ICP A          
      71 K-mount Allocations          
      72 Alignment TBRs          
      73 Telemetry Rate TBRs          
      74 MIPS          
      75 Survival Loads          
      76 FSW Data Rate          
NIRCam Needs
Need Status ECD Assigned