Date Event Details
7/12/05 Optical Bench Assy CDR Palo Alto, CA
7/13/05 Stray Light Baffles CDR Palo Alto, CA
7/19-21/05 JWST Quarterly Victoria, BC, Canada
7/19-21/05 SIDU Upgrade Palo Alto, CA
7/25-26/05 WFSC Mini-PIT Boulder, CO
7/26-27/05 ICDH PDR GSFC
7/26/05 FIlter Wheel CDR Palo Alto, CA
7/27/05 PIL CDR Palo Alto, CA
7/28/05 3-DOF FAM CDR Palo Alto, CA
8/4/05 Thermal CDR Palo Alto, CA
8/8-9/05 NIRCam Science Team Mtg Palo Alto, CA
8/25/05 NIRCam Monthly Palo Alto, CA
8/31/05 FPA Housing CDR Palo Alto, CA
9/27/05 ICE CDR Palo Alto, CA
9/28/05 FPE CDR Palo Alto, CA
9/29/05 FSW CDR Palo Alto, CA

Last Week's Accomplishments

1) Received cert logs from Ball which were the
final items to be shipped in the close out of the
Ball sub-contract. Inspection of the logs reveals that
that SCA plates are machined very accurately supporting
"bolt and go" construction.
2) Prepared various sensitivity charts and analyses for the SAT.
3) Created a NIRCam News Web page.
4) Completed board layout for the ASIC Test Board.
5) Selected connectors for the ICE cables.
6) Conducted another software peer review on a code module. About
half of the issues uncovered at the previous peer review have been
resolved.
7) Submitted 3-month Slip proposal.

Announcements

Mitra Dutta is organizing another order of ISIM-logo merchandise from Land's End. Contact Mitra (mdutta@pop200.gsfc.nasa.gov) if you're interested.

 

NIRCam Top 5
  Item Status Action Next Report
1 FY06 Funding NIRCam team determing schedule impact Telecon w/Pam S. 7/7/05
2 Requirements      
3 Detector Packaging      
4 Detector BCS Failure    

7/13/05

5 Filter Wheel Accuracy   Expect resolution @ FWA CDR 7/26/05
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd On hold for resolution of NOTES testing plan.
SA-14 Safety Plan Rejected 6/23/2005 Need to work with J. Rauscher to resolve.
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd PAR2MAR     Replace PAR with MAR Rev A. Yes Negotiations 7/1/05    
tbd 3-mo schedule slip     3-Month Schedule Slip Yes Tech Eval 7/8/05    
tbd Wave 4     Wave 4 Changes yes RFP tbd    
    207   NIRCam Spec Rev B (PDR) yes Complete      
    231   IRD Rev A. yes Complete      
    235   DMGSER Rev A

yes

Complete      
    236   GFP List Rev. A yes Complete      
    259   Mech GSE in Contract B.1 yes Complete      
    268   Contract Attachment N no Complete      
tbd Wave 5     Wave 5 Changes yes        
    tbd   X month Schedule Slip yes draft      
    313   SOW Rev E (Test Changes) Yes CCB      
    tbd   MAR Rev B Yes Draft      
    320   IRD Rev C Yes Comment 7/8/05    
      019D NIRCam Discretes no Complete      
      020A Focus no Complete      
      021A Pupil Shear no Complete      
      022A Code Format no Complete      
      023C Launch Pressure Profile no Complete      
      024B V1 Down Testing no Complete      
      027B NIRCam Fault Protection no Complete      
    312   ISIM Requirements Doc Rev A   CCB 7/5/05    
    tbd   NIRCam Spec Rev C          
tbd Wave 6     Wave 6 Changes          
    tbd   IRD Rev D   Draft      
      008B Thermal   Loop 3      
      015B I&T Test Aids   Loop 3      
      017A On Orbit Sine   Loop 3      
      018A Radiative Heat Transfer   Loop 3      
      025A PIL Distortion   Loop 3      
      026A Mechanisms   Loop 3      
      028A ASIC   Loop 3      
      030A FSW Telemetry Rate   Loop 3      
      031A PIL Image & WFE   Loop 3      
      032A WFS&C   Loop 3      
      tbd TBD/TBR reduction   draft      
tbd tbd tbd   IRD Rev E          
      029A I&T Aids   Loop 1      
      033A Electrical TBRS   Loop 1      
      034A Outgassing Rate   Loop 1      
      035A PIL WFE   Loop 1      
      036A Structural Interface Load   Loop 1      
      041A Radiation   Loop 1      
NIRCam Needs
Need Status ECD Assigned  
Requirements Baseline by July 31 See "Pending Changes" above. 7/31/05 TBR Lundquist  
Index measurements of fused silica Kepler tests started 6/14 6/30/05 Leviton  
Mechanical ICD EO2 release EO1 & EO2 expected final by Bench CDR 7/12/05 Carter  
ASIC Ops Concept & interface documents ops concept out for review   Dutta  
Additional SWTS for SIDU+ #2     Campbell  
Guidance on financial planning for FY06 Telecon with Pam Sullivan on 7/7/05   Sullivan  

NIRCam TBD/TBR Progress & Plan