Logo

NIRCam News
June 28, 2005

Tuesday Telecon

Tuesday, June 28; 1600 EDT
Goddard Location: 22/399
Dial-in: 877-951-3250, Code 108321

Agenda: Mechanical - OBA testing & K-mount availability
    Mechanical - FPE Harness Routing & Connector Panel
    RTC & Pending Changes Planning - see below
    

 

NIRCam Calendar
Date Event Details
7/12/05 Optical Bench Assy CDR Palo Alto, CA
7/13/05 Stray Light Baffles CDR Palo Alto, CA
7/19-21/05 JWST Quarterly Victoria, BC, Canada
7/25-26/05 WFSC Mini-PIT Boulder, CO
7/26-27/05 ICDH PDR GSFC
7/26/05 FIlter Wheel CDR Palo Alto, CA
7/27/05 PIL CDR Palo Alto, CA
7/28/05 3-DOF FAM CDR Palo Alto, CA
8/4/05 Thermal CDR Palo Alto, CA
8/8-9/05 NIRCam Science Team Mtg Palo Alto, CA
8/25/05 NIRCam Monthly Palo Alto, CA
8/31/05 FPA Housing CDR Palo Alto, CA
9/27/05 ICE CDR Palo Alto, CA
9/28/05 FPE CDR Palo Alto, CA
9/29/05 FSW CDR Palo Alto, CA

Last Week's Accomplishments

1) Meeting to close Ball packaging contract held at Ball
with inventories, drawings, and cert logs reviewed.
2) Residual parts from Ball packaging contract received at Arizona.
3) Began an exercise to look at consequence to NIRCam
development if FY06 budget were to be cut about in half.
4) Completed a contamination study that has led to a
design for heaters on the NIRCam pick-off mirrors.
5) A revised design for the short wavelength FPA has been
sent from Arizona to Lockheed Martin for thermal and structural
analysis.

 

Announcements

Mitra Dutta is organizing another order of ISIM-logo merchandise from Land's End. Contact Mitra (mdutta@pop200.gsfc.nasa.gov) if you're interested.

 

NIRCam Optical Bench - 1st Beryllium Part being machined at Axsys. (Photo Axsys Corp.)

NIRCam Top 5
  Item Status Action Next Report
1 Funding      
2 Detector Packaging      
3 Detector BCS      
4 Filter Wheel Accuracy      
5 Instrument Throughput      
Document Status
DRD Title Status Due Comments
SA-01 QA Plan Approved    
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd On hold for resolution of NOTES testing plan.
SA-14 Safety Plan Rejected 6/23/2005 Need to work with J. Rauscher to resolve.
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd PAR2MAR     Replace PAR with MAR Rev A. Yes Negotiations 7/1/05    
tbd 3-mo schedule slip     3-Month Schedule Slip Yes Proposal 6/27/05    
tbd Wave 4     Wave 4 Changes yes RFP tbd    
    207   NIRCam Spec Rev B (PDR) yes Complete      
    231   IRD Rev A. yes Complete      
    235   DMGSER Rev A

yes

Complete      
    236   GFP List Rev. A yes Complete      
    259   Mech GSE in Contract B.1 yes Complete      
    268   Contract Attachment N no Complete      
tbd Wave 5     Wave 5 Changes yes        
    313   SOW Rev E (Test Changes) Yes Open      
    tbd   MAR Rev B Yes Draft      
    320   IRD Rev C Yes Comment 7/1/05    
      019D NIRCam Discretes   Complete      
      020A Focus   Complete      
      021A Pupil Shear   Complete      
      022A Code Format   Complete      
      023C Launch Pressure Profile   Complete      
      024B V1 Down Testing   Complete      
      027B NIRCam Fault Protection   Complete      
    312   ISIM Requirements Doc Rev A   CCB 7/5/05    
    tbd   NIRCam Spec Rev C          
tbd Wave 6     Wave 6 Changes          
    tbd   IRD Rev D          
      008B Thermal   Loop 2 7/1/05    
      015B I&T Test Aids   Loop 3      
      017A On Orbit Sine   Loop 3      
      018A Radiative Heat Transfer   Loop 3      
      025A PIL Distortion   Loop 2 7/1/05    
      026A Mechanisms   Loop 2 7/1/05    
      028A ASIC   Loop 2 7/1/05    
      030A FSW Telemetry Rate   Loop 2 7/1/05    
      031A PIL Image & WFE   Loop 2 7/1/05    
      032A WFS&C   Loop 2 7/1/05    
      tbd TBD/TBR reduction   draft      
tbd tbd tbd   IRD Rev E          
      029A I&T Aids   Loop 1      
      033A Electrical TBRS   Loop 1      
      034A Outgassing Rate   Loop 1      
      035A PIL WFE   Loop 1      
      036A Structural Interface Load   Loop 1      
      041A Radiation   Loop 1      
NIRCam Needs
Need Status ECD Assigned  
Requirements Baseline by July 31 See "Pending Changes" above. 7/31/05 TBR Lundquist  
Index measurements of fused silica Kepler tests started 6/14 6/30/05 Leviton  
Mechanical ICD EO2 release     Carter  
ASIC Ops Concept & interface documents     Dutta  
Additional SWTS for SIDU+ #2     Campbell  
Guidance on financial planning for FY06 Telecon with Pam Sullivan on 6/22/05   Sullivan  

NIRCam TBD/TBR Progress & Plan