Logo

NIRCam News
June 26, 2006
Previous editions are available in the archive.

Tuesday Telecon

Tuesday, June 27, 1600 EDT

Goddard Location: 22/C399A

Dial-in: 877-951-3250, Passcode 108321

Agenda: NIRCam Kinematic Mounts and Requirements

NIRCam Calendar
Date Event Details
6/28-29/06 JWST SWG Montreal
7/20/06 NIRCam Monthly Camarillo, CA
7/25-26/06 ISIM Verification and I&T Summit GSFC Area
8/31/06 NIRCam Monthly Palo Alto, CA
9/21/06 NIRCam Monthly Palo Alto, CA
10/18-19/06 JWST SWG Boulder, CO
10/24-26/06 ISIM PDR GSFC Area
10/27/06 NIRCam Monthly GSFC
11/21/06 NIRCam Monthly Camarillo, CA
11/28-30/06 JWST Quarterly Redondo Bch, CA
12/19/06 NIRCam Monthly Palo Alto, CA

Last Week's Accomplishments

NIRCam Activities for Week Ending 06/21/06

1) ICE Team performed an end-to-end test of FWA control using
a flight software simulator to control the DIO board which in
turn controlled the mechanism.
2) Completed two more SCA cable assemblies.
3) Working with MOOG to analyze the actuator life test failure that
resulted from inadequate dichronite lubricant thickness.
4) Supported the ISIM Thermal PDR and the IEC SRR.


Announcements

 

NIRCam Top 5
  Item Status Action Next Report
1 Detector Packaging & Test      
2 Lens Triplet Cryo Test      
3 Filter Wheel Life Test with PFD    

 

4

Electronics drawing release

     
Document Status
DRD Title Status Due Comments
IT-03 Instrument and GSE Ground Transportation Plan Returned for minor corrections 6/5/2006  
PM-01 Project Management Plan Approved    
SA-02 Contamination Control Plan Returned for changes 6/5/2006  
SA-06 Materials Usage List Returned - incomplete 6/9/2006  
SA-07 As Designed Parts List Distr for Review 6/5/2006  
SA-08 Parts Database Distr for Review 6/5/2006  
SA-09 Parts Stress Analysis Approved    
SA-14 Hazard Analysis Distr for Review 6/5/2006  
SE-04 Verification Plan Distr for Review 6/9/2006 Need mtg or telecon to work issues
SE-08 Inputs to IOS ICD Approved    
SE-09 Fault Protection Description Distr for Review 6/9/2006  
SE-10 Math Models Distr for Review 6/30/2006  
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd       Wave 6 Cost Changes yes        
    476   IRD Rev E yes complete      
        NIRCam ETU Spec no        
        NIRCam SOW Rev F yes out for comment   NOTES testing, Grism  
        IRD Rev F no        
      34 Outgassing Rate          
      54 Stray Light #2          
      56 IRSU          
      65 FOV Changes          
      68 ICE Sync Changes          
      70 ICP A          
      71 K-mount Allocations          
      72 Alignment TBRs          
      73 Telemetry Rate TBRs          
      74 MIPS          
      75 Survival Loads          
      76 FSW Data Rate          
NIRCam Needs
Need Status ECD Assigned  
Spacewire ICD & Spec     Aguilar  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  
SIDU Upgrade for ASIC     Guy