NIRCam Calendar
| Date |
Event |
Details |
| 6/22/06 |
NIRCam Monthly |
Palo Alto, CA @ 0830 PDR |
| 7/20/06 |
NIRCam Monthly |
Camarillo, CA |
| 7/25-26/06 |
ISIM Verification and I&T Summit |
GSFC Area |
| 8/31/06 |
NIRCam Monthly |
Palo Alto, CA |
|
Last Week's Accomplishments
NIRCam Activities for Week Ending 6/16/2006:
|
|
NIRCam Top 5
| |
Item |
Status |
Action |
Next Report |
| 1 |
Detector Packaging & Test |
|
|
|
| 2 |
Lens Triplet Cryo Test |
|
|
|
| 3 |
Filter Wheel Life Test with PFD |
|
|
|
| 4 |
Electronics drawing release
|
|
|
|
|
Document Status
| DRD |
Title |
Status |
Due |
Comments |
| IT-03 |
Instrument and GSE Ground Transportation Plan |
Returned for minor corrections |
6/5/2006 |
|
| PM-01 |
Project Management Plan |
Distr for Review |
5/30/2006 |
|
| SA-02 |
Contamination Control Plan |
Returned for changes |
6/5/2006 |
|
| SA-06 |
Materials Usage List |
Returned - incomplete |
6/9/2006 |
|
| SA-07 |
As Designed Parts List |
Distr for Review |
6/5/2006 |
|
| SA-08 |
Parts Database |
Distr for Review |
6/5/2006 |
|
| SA-09 |
Parts Stress Analysis |
Distr for Review |
6/9/2006 |
|
| SA-14 |
Hazard Analysis |
Distr for Review |
6/5/2006 |
|
| SE-04 |
Verification Plan |
Distr for Review |
6/9/2006 |
|
| SE-08 |
Inputs to IOS ICD |
Approved |
|
|
| SE-09 |
Fault Protection Description |
Distr for Review |
6/9/2006 |
|
| SE-10 |
Math Models |
Distr for Review |
6/30/2006 |
|
|
Pending Changes
| Mod |
Mod Descr |
CCR # |
RTC# |
Description |
Cost/No |
Status |
Due |
Comments |
ECD |
| tbd |
|
|
|
Wave 6 No-Cost Changes |
no |
|
|
|
|
| |
|
395R1 |
|
MICD E04 |
|
|
|
|
|
| |
|
486 |
|
MICD EO5 |
|
|
|
|
|
| |
|
490 |
|
MICD EO6 |
|
|
|
|
|
| |
|
493 |
|
MICD EO7 |
|
|
|
|
|
| |
|
494 |
|
1553 Spec Rev B |
|
|
|
|
|
| |
|
416 |
|
DILS Rev H |
|
|
|
|
|
| |
|
n/a |
|
Attachment N Rev E |
|
|
|
|
|
| tbd |
|
|
|
Wave 6 Cost Changes |
yes |
|
|
|
|
| |
|
476 |
|
IRD Rev E |
yes |
complete |
|
|
|
| |
|
|
|
NIRCam ETU Spec |
no |
|
|
|
|
| |
|
|
|
NIRCam SOW Rev F |
yes |
out for comment |
|
NOTES testing, Grism |
|
| |
|
|
|
IRD Rev F |
no |
|
|
|
|
| |
|
|
34 |
Outgassing Rate |
|
|
|
|
|
| |
|
|
54 |
Stray Light #2 |
|
|
|
|
|
| |
|
|
56 |
IRSU |
|
|
|
|
|
| |
|
|
65 |
FOV Changes |
|
|
|
|
|
| |
|
|
68 |
ICE Sync Changes |
|
|
|
|
|
| |
|
|
70 |
ICP A |
|
|
|
|
|
| |
|
|
71 |
K-mount Allocations |
|
|
|
|
|
| |
|
|
72 |
Alignment TBRs |
|
|
|
|
|
| |
|
|
73 |
Telemetry Rate TBRs |
|
|
|
|
|
| |
|
|
74 |
MIPS |
|
|
|
|
|
| |
|
|
75 |
Survival Loads |
|
|
|
|
|
| |
|
|
76 |
FSW Data Rate |
|
|
|
|
|
|
NIRCam Needs
| Need |
Status |
ECD |
Assigned |
|
| Spacewire ICD & Spec |
|
|
Aguilar |
|
| Loads from harness/thermal straps |
|
|
Crow |
|
| Info on ground strap, if any |
|
|
McCloskey |
|
| SIDU Upgrade for ASIC |
|
|
Guy |
|
|
| |
|
|
|