NIRCam News
May 30, 2006
Previous editions are available in the archive.

Tuesday Telecon

Tuesday, May 30, 1600 EDT

Goddard Location: 22/C399
Dial-In Information: 877-951-3250, Passcode 108321

Agenda: Julie will send out agenda separately.

NIRCam Calendar
Date Event Details
6/22/06 NIRCam Monthly Palo Alto, CA
7/20/06 NIRCam Monthly Palo Alto, CA
8/31/06 NIRCam Monthly Palo Alto, CA

Last Week's Accomplishments

NIRCam Activities for Week Ending 5/26/2006

1) Sucessfully completed CDR. CONGRATULATIONS EVERYONE!

Announcements

The NIRCam CDR chart package is available on NGIN as JWST-RVW-002946.

Many NIRCam DRDs were delivered for CDR (see list below). Please review and comment via NGIN.

NIRCam Top 5
  Item Status Action Next Report
1 Detector Packaging      
2 ICD      
3 Budget    

 

4

Cryo Lens Test

     
Document Status
DRD Title Status Due Comments
IT-03 Instrument and GSE Ground Transportation Plan Distr for Review 6/5/2006  
PM-01 Project Management Plan Distr for Review 5/30/2006  
SA-02 Contamination Control Plan Distr for Review 6/5/2006  
SA-06 Materials Usage List Distr for Review 6/9/2006  
SA-07 As Designed Parts List Distr for Review 6/5/2006  
SA-08 Parts Database Distr for Review 6/5/2006  
SA-09 Parts Stress Analysis Distr for Review 6/9/2006  
SA-14 Hazard Analysis Distr for Review 6/5/2006  
SE-04 Verification Plan Distr for Review 6/9/2006  
SE-08 Inputs to IOS ICD Distr for Review 5/30/2006  
SE-09 Fault Protection Description Distr for Review 6/9/2006  
SE-10 Math Models Distr for Review 6/9/2006  
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
039 Wave 5     Wave 5 Changes yes Complete  

 

 
tbd       Wave 6 Changes yes        
    476   IRD Rev E yes complete      
        NIRCam ETU Spec no        
        NIRCam SOW Rev F yes draft   NOTES testing, Grism  
        IRD Rev F no        
      34 Outgassing Rate          
      54 Stray Light #2          
      56 IRSU          
      65 FOV Changes          
      68 ICE Sync Changes          
      70 ICP A          
      71 K-mount Allocations          
      72 Alignment TBRs          
      73 Telemetry Rate TBRs          
      74 MIPS          
      75 Survival Loads          
      76 FSW Data Rate          
NIRCam Needs
Need Status ECD Assigned  
Spacewire ICD & Spec     Aguilar  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  
SIDU Upgrade for ASIC     Guy  

NIRCam TBD/TBR Progress & Plan