Agenda: Thermal Section of ICD
Mass Sims for WFS Parts

NIRCam Calendar
Date Event Details
5/22-23/06 NIRCam CDR Palo Alto, CA
6/22/06 NIRCam Monthly Palo Alto, CA
6/28-29/06 JWST SWG Mtg Montreal, Canada
7/20/06 NIRCam Monthly Palo Alto, CA
8/31/06 NIRCam Monthly Palo Alto, CA
10/18-19/06 JWST SWG Mtg Redondo Beach, CA
10/24-26/06 ISIM PDR GSFC

Last Week's Accomplishments

NIRCam Activities for Week Ending 5/10/2006

1) Finally completed first cable shipment to Rockwell.
2) Major emphasis on preparing for CDR and preparing
the documents to be submitted in support of CDR.
3) A pre-ship review for the the barium fluroide and
zinc sulfide lenses was held at OSI.
4) Bandpass filters CDR held.
5) CDR Dry run held.
6) "Wave 5" contract change completed.


Announcements

The NIRCam Bandpass Filter CDR chart package is available on NGIN as JWST-PRES-006593.

CDR Agenda is attached.

NIRCam Top 5
  Item Status Action Next Report
1 Detector Packaging      
2 ICD      
3 Budget    

 

4        
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd  
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
039 Wave 5     Wave 5 Changes yes Complete  

 

 
tbd       Wave 6 Changes yes        
    476   IRD Rev E yes complete      
        NIRCam ETU Spec no        
        NIRCam SOW Rev F yes draft   NOTES testing, Grism  
        IRD Rev F no        
      34 Outgassing Rate          
      54 Stray Light #2          
      56 IRSU          
      65 FOV Changes          
      68 ICE Sync Changes          
      70 ICP A          
      71 K-mount Allocations          
      72 Alignment TBRs          
      73 Telemetry Rate TBRs          
      74 MIPS          
      75 Survival Loads          
      76 FSW Data Rate          
NIRCam Needs
Need Status ECD Assigned  
Resolve TBXs in NIRCam Reqts Documents See "Pending Changes" above. 7/31/05 TBR Lundquist  
NIRCam Drill template to Axsys delayed by funding runout at GSFC 3/15/06 Crow  
ASIC Ops Concept & interface documents TIM 12/2/2005   Dutta  
Spacewire ICD & Spec     Aguilar  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  
SIDU Upgrade for ASIC     Guy  

NIRCam TBD/TBR Progress & Plan