NIRCam News
May 16, 2006
Previous editions are available in the archive.
|
Tuesday Telecon
Tuesday, May 16, 1600 EDT
Goddard Location: 22/C399
Dial-In Information: 877-951-3250, Passcode 108321
Agenda: Thermal Section of ICD
Mass Sims for WFS Parts
|
NIRCam Calendar
| Date |
Event |
Details |
| 5/22-23/06 |
NIRCam CDR |
Palo Alto, CA |
| 6/22/06 |
NIRCam Monthly |
Palo Alto, CA |
| 6/28-29/06 |
JWST SWG Mtg |
Montreal, Canada |
| 7/20/06 |
NIRCam Monthly |
Palo Alto, CA |
| 8/31/06 |
NIRCam Monthly |
Palo Alto, CA |
| 10/18-19/06 |
JWST SWG Mtg |
Redondo Beach, CA |
| 10/24-26/06 |
ISIM PDR |
GSFC |
|
Last Week's Accomplishments
NIRCam Activities for Week Ending 5/10/2006
1) Finally completed first cable shipment to Rockwell.
2) Major emphasis on preparing for CDR and preparing
the documents to be submitted in support of CDR.
3) A pre-ship review for the the barium fluroide and
zinc sulfide lenses was held at OSI.
4) Bandpass filters CDR held.
5) CDR Dry run held.
6) "Wave 5" contract change completed.
|
Announcements
The NIRCam Bandpass Filter CDR chart package is available on NGIN as JWST-PRES-006593.
CDR Agenda is attached.
|
NIRCam Top 5
| |
Item |
Status |
Action |
Next Report |
| 1 |
Detector Packaging |
|
|
|
| 2 |
ICD |
|
|
|
| 3 |
Budget |
|
|
|
| 4 |
|
|
|
|
|
Document Status
| DRD |
Title |
Status |
Due |
Comments |
| SE-04 |
Verification Plan |
Rejected |
7/27/05 |
|
| IT-01 |
I&T Plan |
Rejected |
tbd |
|
|
Pending Changes
| Mod |
Mod Descr |
CCR # |
RTC# |
Description |
Cost/No |
Status |
Due |
Comments |
ECD |
| 039 |
Wave 5 |
|
|
Wave 5 Changes |
yes |
Complete |
|
|
|
| tbd |
|
|
|
Wave 6 Changes |
yes |
|
|
|
|
| |
|
476 |
|
IRD Rev E |
yes |
complete |
|
|
|
| |
|
|
|
NIRCam ETU Spec |
no |
|
|
|
|
| |
|
|
|
NIRCam SOW Rev F |
yes |
draft |
|
NOTES testing, Grism |
|
| |
|
|
|
IRD Rev F |
no |
|
|
|
|
| |
|
|
34 |
Outgassing Rate |
|
|
|
|
|
| |
|
|
54 |
Stray Light #2 |
|
|
|
|
|
| |
|
|
56 |
IRSU |
|
|
|
|
|
| |
|
|
65 |
FOV Changes |
|
|
|
|
|
| |
|
|
68 |
ICE Sync Changes |
|
|
|
|
|
| |
|
|
70 |
ICP A |
|
|
|
|
|
| |
|
|
71 |
K-mount Allocations |
|
|
|
|
|
| |
|
|
72 |
Alignment TBRs |
|
|
|
|
|
| |
|
|
73 |
Telemetry Rate TBRs |
|
|
|
|
|
| |
|
|
74 |
MIPS |
|
|
|
|
|
| |
|
|
75 |
Survival Loads |
|
|
|
|
|
| |
|
|
76 |
FSW Data Rate |
|
|
|
|
|
|
NIRCam Needs
| Need |
Status |
ECD |
Assigned |
|
| Resolve TBXs in NIRCam Reqts Documents |
See "Pending Changes" above. |
7/31/05 TBR |
Lundquist |
|
| NIRCam Drill template to Axsys |
delayed by funding runout at GSFC |
3/15/06 |
Crow |
|
| ASIC Ops Concept & interface documents |
TIM 12/2/2005 |
|
Dutta |
|
| Spacewire ICD & Spec |
|
|
Aguilar |
|
| Loads from harness/thermal straps |
|
|
Crow |
|
| Info on ground strap, if any |
|
|
McCloskey |
|
| SIDU Upgrade for ASIC |
|
|
Guy |
|
|
NIRCam TBD/TBR Progress & Plan

|
|
|
|