NIRCam News
March 7 , 2006
Previous editions are available in the archive.
|
Tuesday Telecon
Tuesday, March 7, 1600 EST
Goddard Location: 22/C399
Dial-in information: 877-951-3250 passcode: 108321
Agenda: ICD Status, FPE & ICE input review, Outgassing Rate RTC.
|
NIRCam Calendar
| Date |
Event |
Details |
| 3/22/06 |
ICE CDR |
Palo Alto, CA |
| 3/23/06 |
NIRCam Monthly |
Tucson, Az |
| 3/28/06 |
NIRCam I&T CDR |
Palo Alto, CA |
| 3/29-30/06 |
I&T and Verif Mtg |
GSFC |
| 4/4/06 |
FPE CDR |
Palo Alto, CA |
| 4/11/06 |
FWA,PIL CDR Closure |
Palo Alto, CA |
| 4/20/06 |
FSW CDR |
Palo Alto, CA |
| 4/25-27/06 |
JWST Quarterly |
Noordwijk, Netherlands |
| 5/24-25/06 |
NIRCam CDR |
Palo Alto, CA |
| 5/25/06 (TBR) |
NIRCam Monthly |
GSFC |
| 6/22/06 |
NIRCam Monthly |
Palo Alto, CA |
| 6/28-29/06 |
JWST SWG |
Montreal, Canada |
| 7/20/06 |
NIRCam Monthly |
Palo Alto, CA |
| 8/31/06 |
NIRCam Monthly |
Palo Alto, CA |
| 10/25-26-/06 |
JWST SWG |
Boulder, CO |
| 11/28-30/06 |
JWST Quarterly |
Redondo Beach, CA |
|
Last Week's Accomplishments
NIRCam Activities for Week Ending 2/28/06
1) Substantial progress has been made on the ICE and FPE portions of the NIRCam ICD with draft release expected next week.
2) ETU lenses are now in polishing with delivery anticipated on schedule at the end of March.
3) Internal I&T review held in preparation for CDR next month -some work still to be done!
4) Discovered a small discrepancy in the refractive index for the PIL lenses before fab had started. A revised PIL prescirption will be issued next week (less than 0.5% change in one radius of curvature).
5) NIRCam supported the rogue path meeting, FSW Review, and IRSU reviews.
|
Announcements
NIRCam FPA CDR charts are available on NGIN as JWST-RVW-006193.
NIRCam Monthly charts are in NGIN shared files in the NIRCam folder.
|
NIRCam Top 5
| |
Item |
Status |
Action |
Next Report |
| 1 |
Requirements |
see below |
|
|
| 2 |
Detector Packaging |
waiting for flex cables |
|
|
| 3 |
Budget |
|
|
|
| 4 |
Optical Alignment Plan |
|
|
|
|
Document Status
| DRD |
Title |
Status |
Due |
Comments |
| SE-04 |
Verification Plan |
Rejected |
7/27/05 |
|
| IT-01 |
I&T Plan |
Rejected |
tbd |
|
|
Pending Changes
| Mod |
Mod Descr |
CCR # |
RTC# |
Description |
Cost/No |
Status |
Due |
Comments |
ECD |
| tbd |
Wave 5 |
|
|
Wave 5 Changes |
yes |
RFP |
|
|
|
| |
|
312 |
|
ISIM Reqts Doc Rev A |
yes |
Complete |
|
Adds reliability calcs |
|
| |
|
382 |
|
ISIM Reqts Doc Rev B |
|
Complete |
|
|
|
| |
|
TBD |
|
NIRCam Spec Rev D |
yes |
CM |
|
ISIM RD Rev B, IRD Rev D |
|
| |
|
313 |
|
SOW Rev E (Test Changes) |
Yes |
Complete |
|
|
|
| |
|
339 |
|
MAR Rev B |
Yes |
Complete |
|
Adds S/W QA |
|
| |
|
364 |
|
MICD EO# 1, 2, 3,4 |
Yes |
Complete |
|
|
|
| |
|
385 |
|
IRD Rev D |
Yes |
Complete |
|
|
|
| |
|
tbd |
|
NIRCam ETU Specification |
|
Loop 1 |
|
|
|
| tbd |
|
|
|
Wave 6 Changes |
|
|
|
|
|
| |
|
tbd |
|
IRD Rev E |
|
|
11/30/05 |
|
|
| |
|
|
030A |
FSW Telemetry Rate |
|
Loop 2 |
|
|
|
| |
|
|
034A |
Outgassing Rate |
|
Loop 2 |
|
|
|
| |
|
|
039 |
FAM Cover |
|
Loop 1 |
|
|
|
| |
|
|
036A |
Structural Interface Load |
|
Loop 1 |
|
|
|
| |
|
|
040 |
FWA Power-On Hold |
|
Draft |
|
|
|
| |
|
|
041A |
Radiation |
|
Loop 2 |
|
|
|
| |
|
|
049A |
Handling Procedures |
|
Loop 3 |
|
|
|
| |
|
|
050A |
WFS&C #4 |
|
Loop 1 |
|
|
|
| |
|
|
052A |
Moving Target |
|
Loop 2 |
|
|
|
| |
|
|
054A |
Stray Light #2 |
|
Loop 1 |
|
|
|
| |
|
|
056 |
IRSU |
|
Draft |
|
|
|
| |
|
|
057 |
Optical Alignment #2 |
|
Draft |
|
|
|
| |
|
|
059 |
Launch Loads |
|
Loop 2 |
|
|
|
| |
|
|
062 |
OTE Rev B Prescription |
|
Loop 1 |
|
|
|
| |
|
|
065 |
FOV Changes |
|
Loop 1 |
|
|
|
| |
|
|
067 |
Alignment Accomodation |
|
Loop 1 |
|
|
|
| |
|
|
ISIM-12 |
Image Motion |
|
|
|
|
|
| |
|
|
ISIM-15 |
Static WFE |
|
Loop 3 |
|
|
|
| |
|
|
ISIM-16 |
Reliability |
|
|
|
|
|
|
NIRCam Needs
| Need |
Status |
ECD |
Assigned |
|
| Resolve TBXs in NIRCam Reqts Documents |
See "Pending Changes" above. |
7/31/05 TBR |
Lundquist |
|
| NIRCam Drill template to Axsys |
delayed by funding runout at GSFC |
3/15/06 |
Crow |
|
| ASIC Ops Concept & interface documents |
TIM 12/2/2005 |
|
Dutta |
|
| Spacewire ICD & Spec |
|
|
Aguilar |
|
| Loads from harness/thermal straps |
|
|
Crow |
|
| Info on ground strap, if any |
|
|
McCloskey |
|
| SIDU Upgrade for ASIC |
|
|
Guy |
|
|
NIRCam TBD/TBR Progress & Plan

|
|
|
|