NIRCam Calendar
Date Event Details
2/21/06 IRSU SRR GSFC
2/22-23/06 ISIM FSW PDR GSFC
3/23/06 NIRCam Monthly Tucson, Az
3/28/06 NIRCam I&T CDR Palo Alto, CA
4/25-27/06 JWST Quarterly Noordwijk, Netherlands
5/16-17/06 NIRCam CDR Palo Alto, CA
5/25/06 NIRCam Monthly GSFC
6/22/06 NIRCam Monthly Palo Alto, CA
7/20/06 NIRCam Monthly Palo Alto, CA
8/31/06 NIRCam Monthly Palo Alto, CA

Last Week's Accomplishments

NIRCam Activities for Week Ending 2/15/06

1) Held a successful FPA CDR.
2) Held a very useful FPE TIM where progress was made against some of the open ICD issues.
3) Dynaco FPA cables have been received and are being evaluated for use in development unit SCAs.
4) Flight software held a CDR dry run which revealed that there were too many open issues with interfaces to ISIM FSW inthe ASIC and fault management areas to hold a real CDR now.
5) Submitted NIRCam Spec Rev D.

Announcements

NIRCam FPA CDR charts are available on NGIN as JWST-RVW-006193.

NIRCam Monthly charts are in NGIN shared files in the NIRCam folder.

 

NIRCam Top 5
  Item Status Action Next Report
1 Requirements see below    
2 Detector Packaging waiting for flex cables    
3 Budget    

 

4 Optical Alignment Plan      
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd  
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd Wave 5     Wave 5 Changes yes RFP  

 

 
    312   ISIM Reqts Doc Rev A yes Complete   Adds reliability calcs  
    382   ISIM Reqts Doc Rev B   Complete      
    TBD   NIRCam Spec Rev D yes CM   ISIM RD Rev B, IRD Rev D  
    313   SOW Rev E (Test Changes) Yes Complete      
    339   MAR Rev B Yes Complete   Adds S/W QA  
    364   MICD EO# 1, 2, 3,4 Yes Complete      
    385   IRD Rev D Yes Complete      
    tbd   NIRCam ETU Specification   Loop 1      
tbd       Wave 6 Changes          
    tbd   IRD Rev E     11/30/05    
      030A FSW Telemetry Rate   Loop 2      
      034A Outgassing Rate   Loop 2      
      039 FAM Cover   Loop 1      
      036A Structural Interface Load   Loop 1      
      040 FWA Power-On Hold   Draft      
      041A Radiation   Loop 2      
      049A Handling Procedures   Loop 3      
      050A WFS&C #4   Loop 1      
      052A Moving Target   Loop 2      
      054A Stray Light #2   Loop 1      
      056 IRSU   Draft      
      057 Optical Alignment #2   Draft      
      059 Launch Loads   Loop 2      
      062 OTE Rev B Prescription   Loop 1      
      065 FOV Changes   Loop 1      
      067 Alignment Accomodation   Loop 1      
      ISIM-12 Image Motion          
      ISIM-15 Static WFE   Loop 3      
      ISIM-16 Reliability          
NIRCam Needs
Need Status ECD Assigned  
Resolve TBXs in NIRCam Reqts Documents See "Pending Changes" above. 7/31/05 TBR Lundquist  
NIRCam Drill template to Axsys delayed by funding runout at GSFC 3/15/06 Crow  
ASIC Ops Concept & interface documents TIM 12/2/2005   Dutta  
Spacewire ICD & Spec     Aguilar  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  
SIDU Upgrade for ASIC     Guy  

NIRCam TBD/TBR Progress & Plan