Logo 

NIRCam News
February 5, 2007
Previous editions are available in the archive.

 

 

Tuesday Telecon

Dial-in: 877-951-3250, Passcode 108321

Date

Meeting Agenda

GSFC Location

Tuesday, Feb 6 

16:00 EST

Mechanism Micro-dynamics Measurement, ICE harness thermal modeling

Bld 22, room C399

Tuesday, Feb 13

16:00 EST

NIRCam MICD

Bld 22, room C399

 

 

Announcements

Stay tuned for an agenda for the February NIRCam Long-Lead GSE Review. 

 

NIRCam Calendar

Date

Event

Details

Feb 6-7, 2007

SWG Meeting

Ball, Boulder Co

Feb 8, 2007

FOV Discussion

Ball, Boulder Co

Feb 13, 2007

Coronagraph & Source CDR

Palo ALto

Feb 20, 2007

NIRCam Long-Lead GSE Review

Palo Alto, Video

Feb 22, 2007

NIRCam Monthly

Camarillo

Feb 27-March 1, 2007

Fault Mgmt/ Ops / FSW Summit

GSFC

Mar 22, 2007

NIRCam Monthly

Palo Alto

Mar 28-29, 2007

Optics Summit

Greenbelt, NGST ECO

Apr 26, 2007

NIRCam Monthly

Palo Alto

May 22, 2007

NIRCam Monthly

Palo Alto

May 29, 2007

NIRCam GSE CDR

Palo Alto

June 11-14, 2007

JWST Workshop

Dublin, Ireland

 

 

 

Accomplishments of Week Ending

 

 

NIRCam Needs (from Jan 29 MSR)

Need

Date Assigned

Assigned to

ECD

Status

Need PSD information and details of mirror segments for higher fidelity coronagraphic modeling

8/31/2006

Mark Clampin

12/1/2006

Ritva to provide delivery date, discuss at Optical Summit meeting on March 28 and 29

Harness and thermal strap loads on bench and struts – needed confirm load on OBA to finalized structural analysis, to complete strut design, and perform OTM analysis on the OA to determine impact on alignment and WFE

8/31/2006

John Crow

 

in process.  Need FPE xsect info

Resolution of intermediate thermal strapping of harnesses

9/26/2006

Ray L

2/13/07

Need to schedule meeting to discuss thermal budget of ICE harnesses.

ISIM analysis of NIRCam EOL contamination levels

10/31/2006

Ray Levesque

 Provide schedule by 1/31/07

Need to set up meeting to discuss Model.

Resolve FPE simulator requirements

1/30/2007

Art Ferrer

 

Art will provide further info on simulator requirements

Strut design

-Need to investigate more compliant flexures to reduce the bench warping caused by ISIM pad motions

-Need updated design for updated OTM analysis

10/31/2006

John Crow

 

need allowable stiffness from NIRCam team. 

Resolution of Rogue Path

8/31/2006

Pam Davila

 

Optical Summit meeting on March 28 and 29

Update NIRCam MICD

-ETU test cone of light keep-out zone in module A FAM mass simulator

-Increase volume allocation to accommodate FAM covers

-Resolve descrepencey from EO5 on strut pad to SIIP interface

-Definition of harness interface to NIRCam struts

Sept  2006

Gurnie Hobbs

 

In process

Resolve 7 open TBXs in NIRCam IRD –INCU-1682 & INCU-1783

 

J. Van Campen

 

RTCs on hold until KM design is complete

Resolve open RTCs

 

J. Van Campen

 

CCR-676 in process

GSFC approval of submitted RFA Responses

 

 

 

in process

 

 

ISIM Needs

Need

Date Assigned

Assigned to

ECD

Status

KM Strut Design

 

 

 1/16/07

Need completed KM Requirements Document.    NIRCam to complete stiffness sensitivity analysis.  Providing updated schedule assuming requirements complete by Feb 9th.

ICD update to ICE cables section

12/25/06

John McCloskey

2/9/07

In Process.  Need info from NIRCam ICE and FPE

FPE cable cross section dimensions for routing work

 

 

2/6/07

Tony to send xsect dimensions of both cables under consideration.

Input into EOL contamination analysis

 

 

TBD

Need to set up meeting to discuss modeling needs

Test plan for Pathfinder Singlet test and Pathfinder triplet-beamsplitter-triplet test.

 

 

TBD

Received Singlet test plan.  Pathfinder test plan pending completion.

ROM for FPE Software Simulator

 

 

1/31/07

 Pending requirement definition

Provide Data on Passive Friction Device Test.

 

 

1/30/07

ISIM would like to review ASAP.

EM on Lens mount DU tests

 

 

 

ISIM would like this documented and available for review.

 

 

Review RFAs (updated 2/2/07)

CDR RFA

Requester

Action Requested

Assignee

Status

ECD

OBA RFA-3

John Johnston

Peel & shear test, analysis of bonded joints.

Alison Nordt

Need to respond to Johnston's questions.

tbd

OBA RFA-4

John Johnston

Assess MS with FS = 1.5.

Alison Nordt

Need to respond to Johnston's questions.

tbd

OBA RFA-8

Richard Vassar

SE to do independent tolerance analysis

Kevin Bock

Kevin auditing NIR-EM-0152A.  Kurli analyzed optic sensitivity.

tbd

SLB RFA-3

Pam Davila

Worst case clearance analysis.

Brent Biggs

Complete clearance analysis, document and present.

tbd

SLB RFA-5

Pam Davila

STOP analysis results, clearances.

Brent Biggs

Complete OTM analysis, document and present.

tbd

FPA RFA-3

Don Hall

Shielding temp sensor/heater cable.

Erick Young

SPICE model the cable assembly to assess the coupling between  thermometer/heater leads and FPA cable inside the housing.

tbd

I&T-II RFA-4

Bill Eichorn

Correlate warm-to-cold models.

Paul Schweiger

Bill additional request for description of Pathfinder test.

tbd

I&T-II RFA-6

Bill Eichorn

Misalignments in fwd and reverse directions.

Paul Schweiger

Bill requested analysis using wavefront optimization.

tbd

I&T-II RFA-10

John Hagopian

WFE of ambient optics. Null lenses.

Paul Schweiger

John wants ambient WFE w/ null lenses in our Plan. Alan to respond.

Jan-07

I&T-II RFA-11

John Hagopian

Define alignment budget items.

Paul Schweiger

John wants to see the completed analysis. Alan to respond.

Jan-07

I&T-II RFA-14

John Hagopian

Include figure uncertainty in alignment.

Paul Schweiger

John wants to see the completed analysis. Alan to respond.

Jan-07

I&T-II RFA-15

John Hagopian

VIRATAC on each optical element.

Paul Schweiger

John wants to see the completed analysis. Alan to respond.

Jan-07

SYS RFA-4

Pam Davila

Cold triplet & DBS interferometer tests.

Roger Potash

DBS done; awaiting triplet test.