Logo

NIRCam News
January 3 , 2006
Previous editions are available in the archive.

Tuesday Telecon

Tuesday, January 3, 1600 EDT

Goddard Location: 22/C399

Dial-in: 877-951-3250, Passcode 108321

Agenda: RTC on FSW Telemetry Rate (030)


NIRCam Calendar
Date Event Details
1/19/06 NIRCam Monthly Camarillo, CA
1/24-26/06 JWST Mission SDR GSFC
late Jan/06 IRSU SRR GSFC
1/31-2/2/06 JWST SWG Redondo Bch, CA
2/2/06 NIRCam ICE CDR Palo Alto, CA
2/8/06 NIRCam FPE CDR Palo Alto, CA
2/9/06 FPA CDR Palo Alto, CA
2/14/06 NIRCam FSW CDR Palo Alto, CA
2/22-23/06 ISIM FSW PDR GSFC
2/23/06 NIRCam Monthly Palo Alto, CA
3/23/06 NIRCam Monthly Tucson, Az
3/28/06 NIRCam I&T CDR Palo Alto, CA
4/25-27/06 JWST Quarterly Noordwijk, Netherlands
5/25/06 NIRCam Monthly GSFC
6/22/06 NIRCam Monthly Palo Alto, CA
7/20/06 NIRCam Monthly Palo Alto, CA
8/31/06 NIRCam Monthly Palo Alto, CA

Last Week's Accomplishments


Announcements

The NIRCam December monthly charts are available on NGIN as JWST-RPT-005966.

The NIRCam FPA housing CDR charts are available on NGIN as JWST-RVW-005970.

 

NIRCam Top 5
  Item Status Action Next Report
1 Requirements see below    
2 Bench cracks Closed    
3 Detector Packaging waiting for flex cables  

 

5 Budget Launch slip proposal submitted    
Document Status
DRD Title Status Due Comments
SE-04 Verification Plan Rejected 7/27/05  
IT-01 I&T Plan Rejected tbd On hold for resolution of NOTES testing plan.
SA-14 Safety Plan Review & Comment 8/15/05 Delivered 7/29/05
Pending Changes
Mod Mod Descr CCR # RTC# Description Cost/No Status Due Comments ECD
tbd Launch Slip     22-mo Launch Slip, 10-mo delivery slip   tech eval      
    334   10-month delivery slip yes Complete      
    361   22-mo launch slip yes Complete      
    tbd   add'l delivery slip no draft      
    tbd   GFE List Replan Updates no draft      
tbd Wave 5     Wave 5 Changes yes RFP  

waiting for IRD

 
    312   ISIM Reqts Doc Rev A yes Complete   Adds reliability calcs  
    382   ISIM Reqts Doc Rev B   CCB      
    TBD   NIRCam Spec Rev D yes draft   ISIM RD Rev B, IRD Rev D  
    313   SOW Rev E (Test Changes) Yes Complete      
    339   MAR Rev B Yes Complete   Adds S/W QA  
    364   MICD EO# 1, 2, 3 Yes Complete      
    385   IRD Rev D Yes CCB      
    tbd   NIRCam ETU Specification   Loop 1      
tbd       Wave 6 Changes          
    tbd   IRD Rev E     11/30/05    
      030A FSW Telemetry Rate   Loop 2      
      034A Outgassing Rate   Loop 1      
      036A Structural Interface Load   Loop 1      
      041A Radiation   Loop 2      
      049A Handling Procedures   Loop 1      
      050A WFS&C #4   Loop 1      
      052A Moving Target   Loop 2      
      054A Stray Light #2   Loop 1      
NIRCam Needs
Need Status ECD Assigned  
Resolve TBXs in NIRCam Reqts Documents See "Pending Changes" above. 7/31/05 TBR Lundquist  
NIRCam Drill template to Axsys delayed by funding runout at GSFC 10/15/05 Crow  
Cryo refractive index measurements of Si Fused Silica complete   Leviton  
ASIC Ops Concept & interface documents TIM 12/2/2005   Dutta  
Spacewire ICD & Spec     Aguilar  
Loads from harness/thermal straps     Crow  
Info on ground strap, if any     McCloskey  
SIDU Upgrade for ASIC     Guy  

NIRCam TBD/TBR Progress & Plan